Construction of the sound walls along North Gate Road is now complete!
It is anticipated that crews will finish paving along the northwest wall and construct the monument for the Seal Beach Boulevard bridge this month.
Additionally, crews will begin drilling operations for the foundation of a freeway sign near the southbound I-405 loop off-ramp to Seal Beach Boulevard.
Drilling activities are anticipated to begin as early as Thursday, Dec. 8, 7 a.m. to 4 p.m. Crews may mobilize equipment as early as 6 a.m., and some activities may occur from 9 p.m. to 6 a.m. as needed.
Lastly, crews will begin installation of water meter, drainage ditch, and electrical services in early-to-mid 2023. It is anticipated that this work will take place behind the current work zone.
Sign up for project-wide and bridge-specific construction alerts at
bit.ly/405-signup.