Construction Update
Exit 16 DDI
DATE: Wednesday, February 8, 2023
 
TRAFFIC IMPACT AND DURATION:
Crews will be onsite Monday through Friday between the hours of 7:00 a.m. and 5:00 p.m. Traffic impacts will be restricted to the hours of 9:00 a.m. and 4:00 p.m. Monday through Friday.

Starting TOMORROW, Thursday, February 9, and continuing through next week, crews will continue working behind the bridge piers on both sides of the interstate bridges over U.S. Routes 2/7 (U.S. 2/7) under lane closures and width reductions.

This work will require closures of the outermost lanes on U.S. 2/7 in both directions. In addition, lane width reductions along the I-89 southbound onramp on the east side of U.S. 2/7 and the I-89 southbound offramp on the west side of U.S. 2/7 will be in effect. The I-89 ramps will remain open.
CONSTRUCTION ACTIVITIES: 
Crews will continue preparing the area behind the bridge piers on both sides of the interstate bridges over U.S. 2/7 to facilitate the installation of retaining walls. Starting tomorrow, Thursday, February 9, and continuing over the next several weeks, crews will be working on both sides of U.S. 2/7 simultaneously.

Along the east side of U.S. 2/7, crews will continue removing material and shoring (installing temporary structural reinforcement) the excavated area in preparation for the installation of the retaining wall starting Friday, February 10. Next week, crews will continue installing the retaining wall. This work will be completed under lane closure of the outer northbound travel lane on U.S. 2/7 and lane width reduction of the I-89 southbound onramp. 

Along the west side of U.S. 2/7, crews will begin removing material including ledge over the next several weeks to facilitate the installation of retaining walls. This work will include hammering to break up the ledge for removal. This work will be completed under lane closure of the outer southbound travel lane on U.S. 2/7 and lane width reduction of the I-89 southbound offramp. 
Crews work to install temporary structural reinforcement (shoring) under the east interstate bridge abutment to facilitate the installation of the retaining wall. The retaining wall will provide access for pedestrians and bicyclists temporarily throughout phase 2 construction and permanently through the installation of the future shared-use path.
LOCATION: U.S. Routes 2/7 (U.S. 2/7) in Colchester starting at the Winooski town line and continuing north for 1.05 miles to Sunderland Woods Road.

PROJECTED COMPLETION: Contract 1 Fall 2023 / Contract 2 Summer 2026
Construction Public Meeting Materials
VTrans held a Construction Public Meeting for the Exit 16 DDI Project on Thursday, January 12, 2023. The meeting included a presentation comprised of an overview of the project, the construction schedule and sequence, the anticipated impacts, and information about future blasting activities. View the presentation and watch the recording of the public meeting!
Diverging Diamond Interchange Comes to Vermont Educational Video
This video provides an overview of the Exit 16 DDI project, discusses the benefits of the Diverging Diamond Interchange design, and demonstrates how drivers, cyclists and pedestrians will navigate the new traffic pattern coming to Colchester, VT.

Translated Materials
VTrans is committed to providing a comprehensive and robust communications and public outreach program as part of this project. 

The project website has been upgraded to include a translation feature with the ability to automatically translate website content into 11 languages. 

In addition, the website is now home to a translated materials tab which includes several frequently asked questions and answers that have been translated into 11 languages with help from trained interpreters and translators from AALV in Burlington, Vermont. 

Contact Us!

24 Hour Project Hotline - 802-595-4399