Construction at the Lane Channel along southbound SR-55 between Dyer Road and MacArthur Boulevard is progressing. Contractors are building forms, pouring concrete, and installing rebar for the channel wall. These activities along with excavation work will continue through early summer.
Retaining Walls
Crews are constructing multiple retaining walls along northbound and southbound SR-55, with several more planned to start in the coming months.
Electric and Drainage
During daytime and nighttime hours, contractors continue to install or relocate electrical and drainage facilities along both directions of SR-55.
|