SHARE:  
OCTA_SR-55 Improvements Logo_Horizontal.png

Week of July 1, 2024

Haga clic aquí para ver esta informacíon en español.

Lane Channel Shoring Installation

WHAT:

Contractors are expected to resume the installation of temporary shoring at the southern end of the Lane Channel, north of MacArthur Boulevard. Businesses adjacent to this work may be impacted by noise and vibration.


WHEN: 

Shoring activity is anticipated for 6 a.m. to 5 p.m. beginning as early as Wednesday, July 3, and continuing intermittently through mid-July.


This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Coming Soon: Northbound MacArthur Boulevard Off-Ramp 10-Day Closure

Crews are planning to reconstruct the northbound MacArthur Boulevard

off-ramp to accommodate the freeway improvements. This work requires a 10-day consecutive closure of the off-ramp. Additional information will be provided in future communications.

Independence Day

In observance of Independence Day, there will be no closures scheduled Wednesday, July 3 through Monday, July 8.

Closures and Detours Map

Bookmark the closures and detours map for quick access to real-time construction information. Click on the construction icons to view activities and closures.

About the Project

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction. Also, the project will add merge lanes between several interchanges and stripe carpool lanes for continuous access, augmenting safety on the freeway by making merging easier. These enhancements are expected to create a better, smoother driving experience for motorists.