Storm system being installed on east side of project.

Storm system being installed on east side of project.

January Meeting Highlights


Project is 50% complete.

  • Contractor has completed the water line installation from Strickland Plaza to Sowers Road. Next steps are completing multiple water tie-ins into the new system.
  • Storm box culvert systems are installed on the east side of the project up to the Griff’s Hamburgers/Subway area. 
  • Installation of the sewer system from the east is approximately within 200 feet of Britain Road. 
  • Demo work continues on the north side of Irving Boulevard, between Main Street and O’Connor Road. 
  • Contractor has prepared the Irving Boulevard subgrade for main lane paving between Britain Road and Jefferson Street. 

Main lane paving preparation looking east at Jefferson Street.

Main lane paving preparation looking east at Jefferson Street.
Concrete placement on north side of Irving Boulevard between Main and Hastings Streets.

Concrete placement on north side of Irving Boulevard, between Main and Hastings Streets.

What is happening this month?

  • Contractor will continue the installation of the storm system on the east side of the project.
  • Contractor will continue paving preparation for the south side of Irving Boulevard at Britain Road to Second Street, and the north side of Irving Boulevard between Main Street and O’Connor Road . 
Map of infrastructure progress on Irving Blvd through January 2023

FAQs


When the sidewalks be replaced? 

Sidewalks along the south side of Irving Boulevard between Hastings Street and Britain Road do not have a definitive date for replacement. City staff will coordinate with businesses along the area for logistics and replacement schedule. 


My customers are having a hard time finding my business. What type of signage can businesses have during this time? 

To assist businesses promoting their operations, there is a temporary suspension of the sign ordinance enforcement for businesses within the construction area. This allows businesses to use signage such as A-frames, flags and banners. While enforcement is suspended during this construction period, placement of signs should not unnecessarily block sidewalks or interfere with traffic on the street or in the construction areas.

Watch the January Meeting

View the January stakeholder meeting presentation.

If you received this message from a friend, subscribe for project updates.

Screenshot of the recorded January meeting

NEXT STAKEHOLDER MEETING: FEB. 14


The next monthly stakeholder meeting will be Tuesday, Feb. 14 at 10 a.m. at the Jack D. Huffman Building, 801 W. Irving Blvd. 


Can’t attend in person?

No problem. Attend virtually via Zoom:


https://us02web.zoom.us/j/86324798030?pwd=T29RZTByS1VEVmU0MmQzNjJ2U1VyQT09


Meeting ID: 863 2479 8030

Passcode: 540627

Phone Call-In: (346) 248-7799


If you received this message from a friend, subscribe for project updates.

CONTACT

Imelda Speck

Housing and Redevelopment Senior Manager

City of Irving


P: (972) 721-2398



E: ispeck@cityofirving.org

IHD Branding.png

Sign up for Traffic Alerts and be notified of traffic pattern changes.


Visit CityofIrving.org/Join. Enter your email address and select "Irving Boulevard Reconstruction" under the News Flash category.


Website

Subscribe

News

Design

Background

Facebook  Twitter  Instagram  YouTube  LinkedIn  Web

Design

LinkedIn Share This Email