Week of May 1
Working: Estes to Greeley
Due to weather and wet conditions, crews were delayed in completing some of the water works improvements. Late last week they were able to finish installing the water main and passed all testing requirements. They will start lateral tie-ins to Freemont and Charlotte and Greeley and Charlotte should completed during this week. During these tie-ins, customers may experience water interruptions that could last up to 2 hours. Residents will be notified of water service interruptions 48 hours in advance. Reinforced Concrete Pipe installation for the stormwater started last week and should be completed this week as well.
Starting this week, Xcel will be installing the gas main line from Estes to Greeley. The installation of the gas main line will be a 4-week project scheduled to tentatively finish by June 1. Xcel will continue to work after this time on tie-ins to the main.
|