Paving on Purdue Circle is anticipated as early as Wednesday, Nov. 30.
Soil backfill, concrete paving, and rock/stone installation is ongoing and anticipated to continue through December.
Final paving of the SB I-405/WB SR-22 connector is ongoing and anticipated to continue through early 2023.
Sound wall reconstruction is anticipated for early 2023.
Crews may access the work zone, intermittently along College Park Drive and from the WB SR-22 connector, to mobilize equipment as early as 6 a.m., and some activities may occur at night from 9 p.m. to 6 a.m. as needed
Please be advised that this work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.