Pine Street – East and West
TODAY, Friday, September 6, crews will be paving the remaining portion of the shared use path along the west side of Pine Street between Burlington Arts Center and Lakeside Avenue. This work will require short 10–15-minute driveway closures to facilitate the paving of the shared-use path.
Next week, crews anticipate paving the final course of asphalt on the remaining driveways on either side of Pine Street. This work will require driveway restrictions including half-width reductions and full closures where secondary driveways are present. Crews will also perform corrective paving in the southwest corner of the Jackson Terrace lot at the corner of Locust Street at Pine Street. This work will require the temporary restriction of the two parking spaces in that area.
In addition, crews will continue adjusting structures to grade, topsoiling, backfilling hardscape surfaces, sign restoration and general cleanup along either side of Pine Street. East Coast Signals will be onsite installing the Rectangular Rapid Flashing Beacons (RRFBs). This work will require lane closures with one-way alternating traffic or lane shifts.
Pine Street at Howard Street, Marble Avenue, and Kilburn Street
There is the potential for crews to install the foundations for the future bus shelters at the intersection of Howard Street and Pine Street.
Crews will continue installing brick pavers at the raised intersections of Pine Street at Kilburn Street and Marble Avenue. The raised intersections include the area bound by the concrete transitions (as shown in the graphic below). Crews will complete brick work at the intersection of Kilburn Street at Pine Street early next week and begin brick work at the intersection of Marble Avenue at Pine Street. This work will require a single-lane closure with alternating one-way traffic on Pine Street and temporary closures of the side roads at their intersection with Pine Street. Lane reductions and side road closures will be in effect 24 hours a day, 7 days a week while this work is completed. Brick paver installation will be completed one intersection at a time with each intersection taking approximately two weeks to complete.
|