After demolition of the existing wall along the southbound SR-55 MacArthur Boulevard on-ramp, an additional overnight concrete pour is planned for as early as 11:59 p.m., Monday, Aug. 19 to 5 a.m., Tuesday, Aug. 20. This work requires closure of the MacArthur Boulevard straight on-ramp, as well as two outside lanes on southbound SR-55. Click here to view the detour map.
Contractors are making steady progress as they continue to construct the footing, providing a solid foundation for the new wall. The newly designed wall will be approximately 1,440' long with a height ranging from 6' to 18'.
Thank you to the neighboring businesses and communities for your patience while crews construct the wall.
|