I-495 (CAPITAL BELTWAY)
I-495 North
Monday, April 17, through Thursday, April 20, 10 a.m. to 3 p.m.
Single right lane closures on northbound I-495 between Lewinsville Road and George Washington Memorial Parkway for sound wall demolition, jack and bore work, and abutment work.
Monday, April 17, through Saturday, April 22, 11 p.m. to 5 a.m.
Triple left lane closures on northbound I-495 between Lewinsville Road and George Washington Memorial Parkway for joint repair work. Note: this work is scheduled to take place nightly through the spring as weather conditions allow.
Monday, April 17, through Friday, April 21, 10 a.m. to 3 p.m. and 9:30 p.m. to 5 a.m.
Alternating mobile single lane closures on northbound I-495 throughout the project corridor as needed for traffic management.
I-495 South
Monday, April 17, through Thursday, April 20, 9:30 a.m. to 2:30 p.m.
Single right lane closures on southbound I-495 between Lewinsville Road and George Washington Memorial Parkway for sound wall demolition, jack and bore work, and abutment work.
Monday, April 17, through Friday, April 21, 10 p.m. to 5 a.m.
Double left lane closures on southbound I-495 between George Washington Memorial Parkway and Old Dominion Drive for median excavation and pipe work.
Monday, April 17, through Friday, April 21, 9:30 a.m. to 2:30 p.m. and 9:30 p.m. to 5 a.m.
Alternating mobile single lane closures on southbound I-495 throughout the project corridor as needed for traffic management.
|