South Old Woodward Reconstruction Phase 3 Project Update
July 5, 2022
Progress Update
Last week the contractor completed the installation of the bioswale concrete along the south end of the project and significant sewer connections along the north end of the project. 

This week, the contractor will continue to work on the installation of the new sewer sections, as well as subgrade preparation and stone placement for the northbound travel lane. The electrical contractor continues to work on the placement of conduit for the median and the east side of South Old Woodward Avenue. 

Sidewalk Access and Parking
Sidewalk access and free 2-hour parking information can be found here.
For more information, contact the Engineering Department at 248-530-1850 or visit www.bhamgov.org/oldwoodwardphase3. We appreciate your patience and look forward to a successful project!
South Old Woodward Reconstruction Phase 3 Project Overview
The South Old Woodward Reconstruction project is the third phase in the City’s plan to improve infrastructure in downtown Birmingham. When complete, South Old Woodward's improvements will allow it to manage traffic more effectively; provide an attractive experience for pedestrians, bicyclists and motorists; and serve the community for decades to come! Learn more by visiting the project webpage at www.bhamgov.org/oldwoodwardphase3Download the construction detour route here.
Learn about City resources and more by visiting www.bhamgov.org, liking the “City Government of Birmingham, MI” Facebook page and following @bhamgov on
 Instagram and Twitter

Join the City's Citywide Email List at www.bhamgov.org/citywideemail

Sign up to receive updates about topics specific to your interests at bit.ly/bhamnews.