Progress Update
Last week the contractor completed the installation of the bioswale concrete along the south end of the project and significant sewer connections along the north end of the project.
This week, the contractor will continue to work on the installation of the new sewer sections, as well as subgrade preparation and stone placement for the northbound travel lane. The electrical contractor continues to work on the placement of conduit for the median and the east side of South Old Woodward Avenue.
Sidewalk Access and Parking
Sidewalk access and free 2-hour parking information can be found here.