CONSTRUCTION ACTIVITIES, DURATION, AND TRAFFIC IMPACTS:
Crews will be on-site Monday, July 25, through Friday, July 29, between the hours of 7:00 a.m. and 7:00 p.m.
Throughout the week, crews will continue work on the installation of the stormwater sand filter located off the roadway just west of the Champlain College Miller Building on Lakeside Avenue and the installation of the additional stormwater drainage infrastructure leading into the sand filter. Work includes excavating the area where the sand filter will be located and installing the stormwater drainage within the project Right of Way along the east side of the parking area between Lakeside Avenue and Sears Lane.
Potential for work to take place stripping topsoil along the east side of Briggs Street between Flynn Avenue and Ferguson Avenue within the project Right of Way to prep the area to stage construction equipment and materials including stormwater structures.
Work will continue off the roadway to the west of Pine Street between Sears Lane and Flynn Avenue. Crews will continue to excavate the area for the stormwater detention pond the location of the box culvert in preparation for installation. Ground improvements will continue throughout the area where the future culvert work will take place for Englesby Brook. Ground improvement work will continue over the next several weeks and will include noticeable vibrations.
|