FRANKLIN & BIRCH ROUNDABOUT PROGRESS
Great progress has been made by the hard-working crews who have finished the majority of the excavation of the project. Remaining excavation will be completed when private utility crews are finished relocating private utilities.
During the next couple of weeks, they will begin the installation of new storm drain facilities, gravity irrigation systems, new domestic water and pressurized irrigation valves. Pole foundations will be poured for flashing crosswalk lights and new light poles. Private overhead utilities will be relocated underground.
Thank you for the patience from the community and the businesses located in the area. Just a reminder the local businesses are still currently open through construction! The crews are working hard to get this project completed as soon as possible. For additional questions, call (208) 565-5262 or email projects@cityofnampa.us.
|