Week of Feb. 10, 2025

Haga clic aquí para ver esta informacíon en español.

Newport Avenue Lane Closure

Contractors are scheduled to perform utility work on Newport Avenue between El Camino Real and Nisson Road. Inside lanes on Newport Avenue will be closed in each direction from 9 p.m. to 5 a.m. Monday, Feb. 10, as well as Wednesday, Feb. 12 through Friday, Feb. 14. At least one lane in each direction will remain open during this time.

Northbound MacArthur Boulevard Loop

On-Ramp Extended Closure Update

Work is underway to reconstruct the northbound SR-55 MacArthur Boulevard loop 

on-ramp, which required an extended closure of the ramp. Due to inclement weather, the ramp is now expected to reopen to motorists on Tuesday, Feb. 18.

Closures and Detours Map

Bookmark the closures and detours map for quick access to real-time construction information. Click on the construction icons to view activities and closures.

About the Project

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction. Also, the project will add merge lanes between several interchanges and stripe carpool lanes for continuous access, augmenting safety on the freeway by making merging easier. These enhancements are expected to create a better, smoother driving experience for motorists.