If you have driven by West this summer you know that the construction work is moving full-speed ahead across several areas in the building.
Interior renovations are starting to take shape. Demolition and environmental work are complete in the Van Hise wing and rough-ins for utilities are well underway. Crews are painting, installing flooring, polishing concrete, and doing ceramic tile work.
Excavation work is wrapping up in the main area of the additions and the earth retention system is almost completely installed. Workers have also started installing the first concrete footings, which will be used to support the concrete masonry walls (CMU) for the exterior of the new gym and pool.
You can find out more about district construction updates and timelines at this link.