55-HOUR FREEWAY LANE AND RAMP CLOSURES 

Friday, May 20 at 10:00 p.m. through Monday, May 23 at 5:00 a.m. 


The three right lanes of westbound (WB) I-10 from Vineyard Avenue to 4th Street will be closed while crews remove and repave lanes. The WB I-10 Vineyard Avenue on-ramps and the 4th Street off-ramp will also be closed and detour routes will be posted. 

WB I-10 EUCLID AVENUE ON-RAMP CLOSURE

Friday, May 20 at 9:00 p.m. 


The WB I-10 on-ramp from southbound (SB) Euclid Avenue will temporarily close for construction for approximately seven months. 

  • Motorists can access the WB I-10 Euclid Avenue loop on-ramp from a new left-turn only lane. 
  • Temporary traffic lights will be in place to assist motorists entering the WB I-10 loop on-ramp. 
  • Parking on SB Euclid Avenue from 8th Street to 7th Street will be prohibited. 



Click here to watch the webinar that provides detailed information about these changes. 

UPCOMING ACTIVITY

As construction continues on the I-10 Express Lanes, crews are working throughout the ten-mile corridor on demolition and reconstruction of bridges, retaining walls, sound walls, utility relocation, and pavement rehabilitation. There are several street and ramp modifications, freeway closures, 55-hour lane closures, and 10-day ramp closures being scheduled. Dates are subject to change. Additional information including detours will be shared and posted to the project Google Map at goSBCTA.com/i10corridor. Upcoming activities include:

55-Hour Freeway Lanes and Ramp Closures for Pavement Operations: 

  • Scheduled to begin Friday, June 3 at 10:00 p.m. through Monday, June 6 at 5:00 a.m. three lanes of EB I-10 from 4th Street to Vineyard Avenue will be closed. The EB 4th Street on-ramp and Vineyard Avenue off-ramp will be closed and detour routes will be posted. 
LEARN MORE ABOUT I-10 EXPRESS LANES CONSTRUCTION IN YOUR CITY
(Click the green boxes below)
MONTCLAIR
ONTARIO
UPLAND

CONSTRUCTION ACTIVITIES -

Week of May 23, 2022

Construction will generally occur Monday through Friday during daytime (6:00 a.m. to 4:00 p.m.) and nighttime (9:00 p.m. to 5:00 a.m.) hours, except as noted. All construction is dynamic and the schedule is subject to change. Please check the Google Map for the most updated closure and detour information.
BRIDGES

Eighteen bridges throughout the corridor are being replaced, widened, or improved to accommodate the widening of the freeway. Work on the bridges may be loud and you may feel vibration at times during both daytime and nighttime hours.


Below is an overview of the current bridge work:


  • San Antonio Creek Channel: The I-10 over San Antonio Creek is being widened. This work began in August 2021.


  • Monte Vista Avenue: Crews continue to relocate underground utilities at Monte Vista Avenue and are building a new center median of the freeway. Work on Monte Vista Avenue began in spring 2020. Monte Vista Avenue under I-10 is reduced to one lane in each direction during daytime hours and will be closed nightly from 7:00 p.m. to 5:00 a.m. Monday through Saturday. Daytime and nighttime activities include installing approach slabs, pouring concrete, and relocating utilities and drainage.


  • Central Avenue: A portion of the EB and WB I-10 shoulder over Central Avenue was removed. Crews are building wider sections of the bridge. Central Avenue may be reduced to one lane in each direction during nighttime hours. Daytime and nighttime activities include installing steel plates into the ground (shoring) in the middle of the bridge.


  • Benson Avenue: A portion of the EB and WB I-10 shoulder over Benson Avenue was removed and is being rebuilt into a wider configuration. Benson Avenue is reduced to one lane in each direction during daytime hours and may be intermittently closed during nighttime hours. Daytime and nighttime activities include earthwork and building portions of bridge footing.


  • Mountain Avenue: The outer portions of the EB and WB I-10 over Mountain Avenue was demolished and will be rebuilt into a wider configuration. Daytime and nighttime activities include building portions of the bridge footing and demolishing portions of the bridge walls next to the WB I-10.


  • San Antonio Avenue: San Antonio Avenue over I-10 is scheduled to be demolished in 2022.


  • Euclid Avenue: Crews demolished and rebuilt the east side of the bridge. The west side of the bridge was demolished in April 2022. SB and northbound (NB) Euclid Avenue approaching I-10 will be intermittently closed from 9:00 p.m. to 5:00 a.m. Daytime and nighttime activities include installing steel plates into the ground (shoring) and building portions of the bridge.


  • Sultana Avenue: The Sultana Avenue bridge over I-10 is now open.


  • Campus Avenue: Campus Avenue over I-10 was demolished in October 2021. Daytime activities include  installing steel plates into the ground (shoring), excavating the bridge walls and building footings.


  • 6th Street: 6th Street over I-10 was demolished in October 2021.


  • Grove Avenue: A portion of the EB and WB I-10 shoulder over Grove Avenue was removed in December 2020. Grove Avenue under I-10 will be closed nightly. Daytime activities include building portions of the bridge and pouring concrete.


  • 4th Street: Crews continue to relocate underground utilities at 4th Street and are building a new wider section of the EB side of the freeway. Work on 4th Street began in spring 2020. 4th Street between El Dorado Avenue and Baker Avenue is reduced to one lane in each direction during daytime hours and will be intermittently closed from 7:00 p.m. to 5:00 a.m., Monday through Friday. Daytime and nighttime activities include building portions of bridge walls and utility installation and relocation.


  • Vineyard Avenue: The east side of Vineyard Avenue over I-10 was partially demolished in March 2021 and is being rebuilt into a wider footprint to accommodate the Express Lanes. Vineyard Avenue over I-10 may have reduced lanes during daytime and nighttime hours. Daytime activities include building portions of the bridge and utility work.


  • Cucamonga Wash Bridge: The EB I-10 over the Cucamonga Wash is being widened. Work began in September 2021. Daytime activities include pouring concrete and utility work.


  • Day Canyon Channel: Work began in August 2021 to widen the I-10 over Day Canyon Channel.
I-10 FREEWAY LANES AND CONNECTORS

Freeway lane closures are necessary for crews to remove trees, perform maintenance, and demolish and rebuild retaining walls, sound walls, and bridges.


  • Friday, May 20 at 10:00 p.m. through Monday, May 23 at 5:00 a.m. three lanes of WB I-10 from Vineyard Avenue to 4th Street will be closed.


  • Scheduled intermittent nighttime connector ramp closures (11:00 p.m. to 5:00 a.m.):
  • NB I-15 to WB/EB I-10
  • SB I-15 to WB I-10


  • Intermittent nighttime lane closures (9:00 p.m. to 5:00 a.m.): EB and WB I-10 between Fairplex Drive and I-15. At least one lane in each direction on I-10 will remain open.


  • Intermittent daytime lane closures: EB and WB I-10 between Indian Hill Boulevard and Euclid Avenue. Four lanes in each direction on I-10 will remain open. These closures will occur between 9:00 a.m. and 2:00 p.m.
I-10 ON- AND OFF-RAMPS

Intermittent nighttime EB and WB I-10 on- and off-ramp and ramp lane closures will occur throughout the project corridor. Detour routes are posted. Please check the Google Map for the most updated information.


  • Friday, May 20 at 10:00 p.m. through Monday, May 23 at 5:00 a.m. WB Vineyard Avenue on-ramps and 4th Street off-ramp will be closed and detour routes will be posted.


  • Beginning Friday, May 20 at 9:00 p.m. the WB Euclid Avenue on-ramp from SB Euclid Avenue will close for approximately seven months. Motorists will be able to access the WB Euclid Avenue loop on-ramp to enter the WB I-10. 


  • Monte Vista Avenue EB on-ramp closed in August 2020 and will be closed for approximately two years. Detour routes include Arrow Highway and Palo Verde Street to Central Avenue.



  • EB I-10 Monte Vista Avenue off-ramp, WB I-10 Monte Vista Avenue on- and off-ramps may be completely closed or limited to right-turns only from 7:00 p.m. to 5:00 a.m.


  • Scheduled intermittent nighttime EB and/or WB on- and off-ramp closures (detour routes will be posted): Indian Hill Boulevard, Mountain Avenue, Euclid Avenue, 4th Street, Vineyard Avenue, Archibald Avenue, Haven Avenue, Milliken Avenue, and Etiwanda Avenue.
LOCAL STREETS AND WALLS

Crews are removing and building sound walls and retaining walls, relocating utilities, and removing trees on several local streets adjacent to the I-10; at times this work may be loud and you may feel vibration. One side of the sidewalk will always remain open. Flaggers may be onsite to direct traffic. Please check the Google Map for the most updated information including closures, detours, and wall locations.


  • Daytime and/or nighttime lane closures (streets will remain open):
  • Monte Vista Avenue, Palo Verde Avenue, Central Avenue, Mountain Avenue, Benson Avenue, San Antonio Avenue, Euclid Avenue, Grove Avenue, 4th Street, Princeton Avenue, and Vineyard Avenue


  • Nighttime street closures (detour routes will be posted); businesses will remain accessible:
  • Monte Vista Avenue: NB/ SB street closed under I-10 (7:00 p.m. to 5:00 a.m.)
  • Palo Verde Street: WB street closed from Central Avenue to Monte Vista Avenue
  • Euclid Avenue: SB street intermittently closed over I-10
  • Benson Avenue: NB/SB street intermittently closed under I-10
  • Grove Avenue: NB/SB street closed under I-10
  • 4th Street: NB/SB street intermittently closed under I-10 (7:00 p.m. to 5:00 a.m.)


  • Retaining wall and sound wall locations:
  • EB I-10: intermittently from Benson Avenue to Haven Avenue
  • WB I-10: approaching Haven Avenue, from 4th Street to Grove Avenue, and intermittently from 6th Street to Central Avenue
ABOUT THE PROJECT
Phase 1 of SB Express Lanes is located in the southwestern portion of San Bernardino County east of Los Angeles County. The project will provide choices on the I-10 freeway between the Los Angeles/San Bernardino County line and I-15. The project includes two express lanes in each direction to offer trip reliability and ease congestion. In addition, lanes to assist drivers getting on and off the freeway (auxiliary lanes) will be constructed in selected locations. West of Haven Avenue, a single new lane will be constructed and combined with the existing HOV lane to provide two express lanes in each direction. The HOV lane will still be available to motorists, but will increase from 2+ to 3+. East of Haven Avenue, two express lanes will be constructed.
Walking on the freeway is unsafe. In case of an emergency, please dial 9-1-1. For non-emergency Freeway Service Patrol (FSP) services, call the California Highway Patrol (CHP) at (909) 428-5400 or use the nearest Call Box for assistance. Drivers or passengers of a disabled vehicle stopped on a freeway may walk to the nearest exit, in either direction, on the same side of the freeway upon which the vehicle is disabled, or to the nearest Call Box for assistance. For the safety of the public and our crews, unapproved access to construction sites and property related to project construction is prohibited.

Sign up for text messages by texting i10expresslanes to (888) 525-1021 (Reply STOP to cancel, text HELP for help. Normal text and data message rates may apply.)

Si prefiere recibir información de construcción en español, llame al (877) 55 - SBCTA.
Wherever you go, FasTrak® is there for you - it can be used on any toll road, lane or bridge in California. For quick access in and around neighboring counties, you can use FasTrak to pay for tolls on the I-15 and 91 Express Lanes in Riverside County; and use the I-10 and I-110 Metro ExpressLanes in Los Angeles County.




877-55-SBCTA
info@gosbcta.com
Facebook  Twitter  Instagram  Linkedin