I-495 (CAPITAL BELTWAY)
I-495 North
Monday, May 15, through Thursday, May 18, 10 a.m. to 3 p.m.
Single right lane closures on northbound I-495 between Lewinsville Road and George Washington Memorial Parkway for sound wall demolition and bridge work.
Monday, May 15, through Saturday, May 20, 11 p.m. to 5 a.m.
Triple right lane closures on northbound I-495 between Dulles Toll Road and George Washington Memorial Parkway for joint repair work. Note: this work is scheduled to take place nightly through the spring as weather conditions allow.
Monday, May 15, through Friday, May 19, 10 a.m. to 3 p.m. & 9:30 p.m. to 5 a.m.
Alternating mobile single lane closures on northbound I-495 throughout the project corridor as needed for traffic management.
I-495 South
Monday, May 15, through Thursday, May 18, 10 p.m. to 5 a.m.
Double left lane closures on southbound I-495 from George Washington Memorial Parkway to Old Dominion Drive for bore pits, backfill, and paving work.
Monday, May 15, through Thursday, May 18, 10 p.m. to 5 a.m.
Double right lane closures on southbound I-495 from George Washington Memorial Parkway to Dulles Toll Road for barrier setting. Note: this work will follow the double left lane closures listed above, there will not be concurrent left and right lane closures.
Monday, May 15, through Thursday, May 18, 9:30 a.m. to 2:30 p.m.
Single right lane closures on southbound I-495 near Old Dominion Drive for bridge work and jack and bore pit work.
Monday, May 15, through Friday, May 19, 9:30 a.m. to 2:30 p.m. & 9:30 p.m. to 5 a.m.
Alternating mobile single lane closures on southbound I-495 throughout the project corridor as needed for traffic management.
|