MacArthur Boulevard Construction Activities

Retaining Wall Concrete Pour

As crews continue constructing the new retaining wall along the southbound MacArthur Boulevard on-ramp, an overnight concrete pour is planned on Wednesday, Oct. 9 from midnight to 5 a.m.


This work will require closing the southbound MacArthur Boulevard straight and loop on-ramps, as well as one outside lane on southbound SR-55 at MacArthur.

Extended Closure of Northbound SR-55 MacArthur Boulevard Off-Ramp

Crews will be pouring concrete on the northbound SR-55 MacArthur Boulevard

off-ramp, which will require an extended closure of the off-ramp. Once the off-ramp reopens, it will be temporarily restriped to include one left-turn and one right-turn lane at the MacArthur intersection. The single lane off-ramp for eastbound MacArthur will be permanently eliminated.


The off-ramp is expected to close as early as 9 p.m., Friday, Oct. 11 and reopen to motorists by 5 a.m., Monday, Oct. 21.


This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Closure and Detour Map.

Temporary Lane Configuration After Extended Closure.

Keep Orange County Clean

Crews continue to conduct efforts to keep the project corridor clean, including the removal of vegetation and weeds, as well as ensure local streets are maintained for pedestrians and motorists. In addition, regular site inspections and sweeps along the mainline are performed.


Help keep Orange County clean! Please report graffiti and trash along the corridor to the Outreach Team at 888-371-2555 or email SR55Info@octa.net.

Closures and Detours Map

Bookmark the closures and detours map for quick access to real-time construction information. Click on the construction icons to view activities and closures.

About the Project

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction. Also, the project will add merge lanes between several interchanges and stripe carpool lanes for continuous access, augmenting safety on the freeway by making merging easier. These enhancements are expected to create a better, smoother driving experience for motorists.

Stay Connected-01.png
Facebook  Instagram  X

octa.net/SR55South

888-371-2555

SR55Info@octa.net

@55FWYProject