W Building Construction Project Update
Week of Nov. 6
Crews will continue demolition of air handlers, associated exhaust systems, roofing material and fans on the roof level. Demolition and installation of ductwork in the mechanical penthouse also will continue. Occupants can expect a lower impact than that experienced during the week of Oct. 30.
Nov. 9: Crane on E. Stoughton Street
On Nov. 9, a crane will be lifting materials onto the roof of the W Building. The crane is expected to be in the street from 5 a.m.-7 p.m. E. Stoughton Street will remain open to through traffic and will be monitored by detail police officers.
Advanced Notice of Auxiliary Power Shutdown Nov. 14-16
There will be three separate 2-hour auxiliary power shutdowns from 5-7 a.m. in the W Building on Tuesday, Wednesday and Thursday, Nov. 14-16.
These shutdowns will affect all red-faced plugs throughout the W building. The construction team and the BU Facilities team will be making accommodations for sensitive pieces of equipment that are on auxiliary power to mitigate issues. Next week a member of the construction team will be going into every room verifying equipment on auxiliary power. A full detailed narrative and plan will be sent out to W Building occupants early next week.
If you have questions/concerns, please contact Dylan McIntosh.
|