*Information provided by Pinellas County and Robin Miller, CEO (from attending meetings and lobbying efforts) ACTION NEEDED SEE BELOW
CURRENT PROJECT:
Passagrille (St. Pete Beach)
- Two-phase projects; 1st phase 10 - 15,000 cubic yards of sand from the Grand Canal
- Starts June 3rd (today)
- Phase 1: 9th Avenue - 22nd Avenue
- It is able to occur because no easements are required (unlike our other beaches which the Army Corps requires perpetual easements)
- All businesses will remain open during the project
- Beach parking and beach access will be open north of the Paradise Grille
- Hours of work: 7 am - 7 pm
ACTION NEEDED: Please download this LETTER on your letterhead and sign.
You can email me robin@tampabaybeaches.com and/or Use this list to send directly to the required recipients. This is vital to help us continue to make progress on Beach Nourishment. DEADLINE: Tuesday, June 4th at Noon.
BARRIER ISLANDS UPDATE:
Our county continues to work tirelessly on the issue of changing the language that requires property owners to sign off on perpetual easements.
Simultaneously, they continue to navigate other solutions.
For more information: 727.464.4600 Pinellas County