Week of May 22
Working: Estes to Greeley
Estes to Greeley and beginning on section from Greeley to Idaho.
Construction will continue on Charlotte from Estes to Greeley and will be focused on the installation of the Xcel gas main.
Provided the water services are completed from last week, crews will start working on Charlotte from Greeley to Idaho. They will mill the roadway between Greeley and Idaho and move the millings over to Charlotte between Estes and Greeley to establish all-purpose roadway. This will allow the section of the roadway to open. After the roadway opens, residents will be responsible for maneuvering their garbage and recycling totes to their usual places.
Greeley will be closed towards the end of this week and Estes will be open (One of these two roadways will be open at all times). Once Greeley is closed, the water lateral connection tie-in into Greeley will be completed since this section of the water infrastructure was delayed.
|