Crews will begin installing utilities in Franklin Road ahead of ITD's SH-16 construction near this area. In order to complete a portion of utilities, Franklin Rd from Star Rd to McDermott Rd will be closed January 23 until early February and reopened again while crews continue to work on the shoulder of the road. Crews anticipate being complete with utilities early August 2023. The widening portion (phase 2) will be constructed after phase 1.
What drivers can expect:
•Franklin Road between Star Road and McDermott Road closed January 23- early February
•Business access available from Star Road
•Future traffic impacts intermittently throughout the project; notification prior
•Crews will be working on the south side of the road majority of the project
For more information, please call (208) 465-2221 or email projects@cityofnampa.us.
|