Latest Contractor Update:
May 2 - installation of rebar sections 9, 10, 11
May 3 - rebar inspections on above
May 4 - concrete pour sections 9, 10, 11
May 5-6 - begin removal of sections 2, 3, 6, 7
Section Locations (2, 3, 6, 7):
2 - Near 7429 Ruston Lane
3 - Near 2314 Creekside Circle S.
6 - Near 2109 Raintree