What to expect
Both of the 7.5 MG tanks are being constructed concurrently, beginning with the floors, then walls and columns, and eventually roof slabs.
Concrete work
Tank #1 roof slab pours are tentatively scheduled for Dec. 29 and Dec. 30. The pump truck will arrive on site around 7 a.m. and concrete will arrive shortly after. We are anticipating each roof section will require around 45 concrete trucks. There will be increased cars parked on E. 40th on roof pour days.
Tree work
EWEB foresters will be on site in the next week to identify hazard trees for removal. EWEB is doing this work to protect neighboring residences and public safety on the site. Tree removal will likely occur before the end of January.
Ferry St. main replacement work
EWEB crews will begin a water main replacement project on Ferry Street north of 43rd Ave. The work involves replacing 500 feet of existing 1950s water infrastructure with a new 8” pipeline, new water services, and a new fire hydrant. The work is schedule to being in early January and will take approximately 2 to 3 weeks to complete. Work hours will be Monday through Thursday and will take place within the City of Eugene’s allowable work hours of 7 a.m - 7 p.m.
Directly impacted neighbors will receive additional communication. If you have any questions or concerns about this work, please contact the EWEB Water Division at 541-685-7595.
Holiday work schedule
Construction crews will be off and there will be no planned work at the site Monday, Dec. 26 and Monday, Jan. 2.