Project enters final weeks until spring
This week, the Central Avenue North Water Improvements project contractor completed the final connection to the new water main.
The remaining work for this season, anticipated to be completed over the next couple of weeks, includes repairing two deficient sewer pipes identified during the project and removing old fire hydrants and gate boxes. A complete paving overlay for Central Avenue is planned for the spring.
Monday, Dec. 27, through Wednesday, Dec. 29:
- The contractor will replace sewer services at 792 and 829 Central Ave.
- When the contractor works at 792 Central Ave., southbound Central Avenue traffic will be detoured around the work site via Lowell Avenue, Mount Vernon Street and Ash Street. Northbound traffic will proceed through the work area.
- When the contractor works at 829 Central Ave., traffic will be reduced to one lane through the project area, alternated by flaggers.
Thursday, Dec. 30:
- The contractor will pave the week's work areas.
- No work is scheduled for New Year's Eve, Friday, Dec. 31. Work will resume Monday, Jan. 3.
- Contact Community Services at 603-516-6450 for more information.