Midland Streetscape Project Update May 5, 2023

Reimagining the Past for a Vibrant Future


Phase 1

Midland Spur Overnight Work

May 10 - May 11

The Midland Spur work is proceeding on schedule. The retaining wall is constructed, utility lines are being put in place and the work has gone smoothly.


If you live and/or work in the vicinity of the Midland Spur, there will be overnight sewer work that begins on May 10 at 7 a.m. and runs through May 11 at 6 p.m. that will be noisy. The reason for the overnight work is to reduce the amount of time sewer service is off-line for customers in the area and to expedite this specific construction activity.


We thank you for your patience while the Town of Basalt undergoes an improvement project that is a once in every 50 years (or more) event. We recognize the inconvenience and look forward to seeing a much improved streetscape when the project is completed.

Midland Spur Progress Shown Above

General Project Information and Newsletters


You can stay tuned to the project at letstalk.basalt.net in English and Spanish. You can contact the project team at midlandstreetscape@gmail.com.


This newsletter you are receiving is for general project information and will be sent when there are project milestones.  


If you would like to receive weekly emails with specific updates on construction information, please sign up here.