Last week, pavement was completed in the following areas:

  • Oakland Road NE, from 35th Street through Hollywood Boulevard, and
  • Hollywood Boulevard NE, from Oakland Road to Richmond Road.

The contractor is now working on replacing side streets, driveways, and sidewalks in these areas.

Over the next two weeks, the contractor will be performing general site cleanup, backfilling dirt, and placing sod on Oakland Road, between Center Street and Hollywood Boulevard, and on Hollywood Boulevard, between Oakland Road and Richmond Road. These sections of roadway are expected to open to local traffic in approximately two weeks, opening the first two stages of this year's three-stage project.

The third and final stage of this year's project, between Hollywood Boulevard and Miami Court, continues. Utility work is ongoing. Paving will follow. This section will remain closed to through traffic while work continues. Signage in place directs southbound through traffic to detour at 42nd Street.

Utility work will also begin soon along Miami Court, with paving to follow. We are finalizing plans to provide as much access to residents in the cul-de-sac as possible. The contractor will reach out to residents directly when access will be affected.

The project's final phase, from Miami Court to Regent Street, will begin next spring when weather allows.

As always, if you have any questions on the project, please don't hesitate to contact us. Thank you for your continued patience!