Scan the QR Code to visit the Clayton County Special Purpose Local Option Sales Tax website where you will find the status and photos of active and completed SPLOST projects. | |
|
Clayton County Special Purpose Local Option Sales Tax (SPLOST) Project Updates | |
Project Details: A new 103,000 sq. ft. three-story Clayton County Administration Building will be located on an 18-acre parcel of land on Old Poston Road in Jonesboro. The facility will be home to several county departments including the Board of Commissioners, Finance, Human Resources, Legal and Communications. | |
Update: The Technical Review Committee (Fire Marshal, Clayton County Water Authority,
Environmental, and Transportation and Development) is looking over the building plans. Once the
review is complete, suggested changes will be sent to the architecture firm to make necessary
any adjustments to the design plans.
| |
Construction Firm:
To Be Determined
| |
Design Firm:
Nelson Worldwide
| |
Project Completion:
To Be Determined
| |
Project Details: New welcome signs will be strategically placed at the north, south, east, and west entrances of the county. The welcome signs showcase the county's new brand logo to welcome and engage citizens and visitors entering the county, including the airport area. | |
Groundscaping around the Gateway Signage begins on September 23, 2024, around the seven Clayton County gateway branded signs at the following locations: Tara Boulevard in Lovejoy; Interstate 75 at Exit 231 NB; Interstate 75 at Exit 235 SB; Interstate 675 at Exit 7; Interstate 75 at Exit 238 NB; Interstate 85 at Exit 71 SB; and Interstate 285 at Exit 60. | |
Construction Firm:
Not Applicable
| |
|
Project Completion:
November 2024
| |
Project Details: The Small Business Incubator will provide resources to introduce, connect, support, and expand new businesses in Clayton County to bolster the creation of jobs, investment, and economic development. | |
The renovation scope of service has been updated. Central Services is preparing to submit the Invitation to Bid. | |
Construction Firm:
To Be Determined
| |
Design Firm:
To Be Determined
| |
Project Completion:
To Be Determined
| |
Project Details: The interior renovations of the Shelnutt Senior Center will include bathroom upgrades, interior lighting replacement, installation of a new washer and dryer, interior wall and ceiling finishes, including wall patching and painting. A new canopy entrance with two new Americans with Disabilities Act (ADA) compliant ramps for accessibility will round out the exterior renovations. | |
Update: The Invitation to Bid to construct a new front canopy closed on September 19, 2024. Central Services is now evaluating vendors who submitted a bid on the project. | |
Construction Firm:
Numerous Contractors
| |
Design Firm:
Gardner Spencer Smith
| |
Completion Date:
To Be Determined
| |
Project Details: The Fleet Maintenance Expansion Project will revitalize the existing facility to include an upgrade to its electrical system, new HVAC, vehicle lifts, flooring, windows, and doors. In addition, a new oil pump system and air lines are planned as well as painting the interior and exterior of the building. | |
Update: The installation of new hoses and reels is expected to begin on September 19, 2024. | |
Construction Firm:
Numerous Contractors
| |
Design Firm:
Not Applicable
| |
Completion Date:
To Be Determined
| |
Project Detail: ProjectThe River's Edge Walking Trail Phase II consists of constructing an asphalt ADA accessible walking trail from Plantation Parkway that will cross over Harbour Town Parkway and continue to Harbour Lake Drive cul-de-sac through 16.32 acres. | |
Update: Final adjustments are being made to the walking trail by Prime Engineering. Sealing and striping is expected to start on September 19, 2024. All work is scheduled to be completed by September 30, 2024. | |
Construction Firm:
Diversified Construction
| |
Design Firm:
Prime Engineering
| |
Completion:
To Be Determined
| |
Project Details: Renovations of the VIP Complex at International Park integrate outdoor spaces while maintaining a multi-functional facility for arts and entertainment. Other enhancements include additional covered seating, event administrative space, dressing rooms, additional concessions, re-design of restrooms, backstage facilities, and vendor kiosks. | |
Update: Documents are being prepared to submit to Central Services for procurement. | |
Construction Firm:
To Be Determined
| |
Design Firm:
Gardner Spencer Smith
| |
Completion Date:
To Be Determined
| |
Project Details: The new Winter Weather Supply and Storage Building will be located behind the Clayton County Jail on Post Way in Jonesboro. The facility will be used to store approximately 14 days of cold weather material such as salt, sand, and gravel. In addition, it will serve as storage for a salt brine maker and brine solution and house snowplows and spreaders. | |
Update: Central Services is preparing to submit an Invitation to Bid requesting design services. | |
Construction Firm:
To Be Determined
| |
Design Firm:
To Be Determined
| |
Completion:
To Be Determined
| |
Project Details: Tennis courts at the International Park Tennis Center, Gerald Matthews Tennis Complex, Independence Park, and Flat Shoals Park will be resurfaced with new fencing and landscaping. The $1.16 million project is estimated to take eight to 10 months to complete. | |
Update: Demolition of the existing courts at the Lovejoy Soccer Complex and removal of fencing has been completed by Signature Tennis Courts Inc. | |
Construction Firm:
Signature Tennis Courts INC
| |
|
Completion date:
October 2024
| |
Project Details: The new Fire Station No. 1 will be a replacement facility for the existing Fire Station No. 1 in Riverdale. | |
Update: The contractor, Hogan Construction Group, is developing a tentative project timeline. | |
Construction Firm:
Hogan Construction Group
| |
Design Firm:
POND & Company
| |
Completion date:
To Be Determined
| |
Project Details: The new Fire Station No. 2 location at 3675 Rex Road in Rex, will be a replacement facility for the existing Fire Station No. 2 at 5239 Ga. Highway 42 in Ellenwood. | |
Update: A scope of service is being written in preparation for the project to go out for bid through Central Services. | |
Construction Firm:
To Be Determined
| |
Design Firm:
POND & Company
| |
Completion date:
To Be Determined
| |
Clayton County Fire Station No. 9 Replacement | |
Project Details:The new Fire Station No. 9 will be located at 4181 Old Dixie Highway. The new station will replace the current facility at 4320 Old Dixie Highway in Hapeville. | |
Update: Albion General Contractors, Inc., located in Sandy Springs, has been awarded the contract to construct Fire Station No. 9, 4181 Old Dixie Highway, Atlanta, Ga. The $6 million project will be funded via the 2004 SPLOST and Fire Funds. | |
Construction Firm:
To Be Determined
| |
Design Firm:
POND & Company
| |
Completion date:
To Be Determined
| |
Project Details: River’s Edge Walking Trail Phase III will begin where Phase II extension ended at Harbour Lake Drive cul-de-sac and run parallel to Fairway Overlook. The trail is just shy of one mile. | |
Update: Clearing work along the planned trail continues with Pride Contracting. | |
Construction Firm:
Pride Contracting Inc.
| |
Design Firm:
Prime Engineering
| |
Completion date:
To Be Determined
| |
Project Details: River’s Edge Walking Trail Phase IV will wrap around the lake between Gleneagles Drive and Gleneagles Way, ending at the clubhouse on Plantation Parkway.
The trail is just shy of one mile. | |
Update: Clearing work along the planned trail continues with Pride Contracting. | |
Construction Firm:
Pride Contracting Inc.
| |
Design Firm:
Prime Engineering
| |
Completion date:
To Be Determined
| |
Morrow-Lake City Park Facility Upgrades | |
Project Details: The Morrow-Lake City Park concession stand and restrooms will be replaced with a new modular building. The project budget is $385,256. | |
Update: BRTU Construction is scheduled to begin demolition of the existing structure on Nov. 1, 2024. In the meantime, designs have been submitted to the building manufacturer for review before fabrication begins. | |
Construction Firm:
BRTU Construction Inc.
| |
|
Completion date:
To Be Determined
| |
Rum Creek Park Facility Upgrades | |
Project Details: The Rum Creek Park concession stand and restrooms will be replaced with a new modular building. The project budget is $378,025. | |
Update: BRTU Construction is scheduled to begin demolition of the existing Rum Creek Park structure on Nov. 1, 2024. In the meantime, designs have been submitted to the building manufacturer for review before fabrication begins. | |
Construction Firm:
BRTU Construction Inc.
| |
|
Completion date:
To Be Determined
| |
Rex Park Facility Upgrades | |
Project Details: The Rex Park concession stand and restrooms will be replaced with a new modular building. The project budget is $376,190. | |
Update: BRTU Construction is scheduled to begin demolition of the existing Rex Park structure on Nov. 1, 2024. In the meantime, designs have been submitted to building manufacturer for review before fabrication begins. | |
Construction Firm:
BRTU Construction Inc.
| |
|
Completion date:
To Be Determined
| |
Please note all dates are subject to change due to numerous
variabilities such as shipping delays and weather.
| |
Access the claytonsplost.com website for more information on projects and improvements throughout Clayton County thanks to voter-approved 1-cent sales tax. | |
Clayton County Board of Commissioners | |
Chairman
Jeffrey E. Turner
| |
Commissioner
Alaina Reaves
District 1
| |
Commissioner
Gail Hambrick
District 2
| |
|
Vice-Chair
DeMont Davis
District 4
| |
Clayton County Board of Commissioners | |
Go Mobile With Us
Get The Click Clayton Mobile App
| | | | |