The general contractor is working on the north end of the project, installing new storm pipe and structures between Shaw Street and Kinnaman Road (west). Other crews are beginning the building and grading of new sidewalk foundations between Celebrity and Farmington roads.
Weather permitting, the contractor is completing the base lift paving of the widened roadway between Celebrity and Farmington roads. Because of the length, the contractor needs several good days of weather to complete this paving work. As the paving work moves northward, side street within this segment will also be base paved. The final lift of asphalt will not be installed until sometime later this summer.
The electrical subcontractor has completed the installation of new electrical conduit, related junction boxes and the street light pole bases, between Celebrity and Farmington Road and is now working on the northern portion of the project.
All work associated with the two new bridges is complete. This includes the relocation of the new sanitary sewer lines around the new bridges structures and the installation of two new water lines through the bridges.
PGE has substantially completed their relocation for the corridor. They have some minor underground connection to make and are still in the area performing line improvements in the adjacent areas as well as making electrical switchover for the telecommunication providers. Contractors for Frontier and Comcast continue relocating their facilities between Jaylee Street and Farmington Road.