OVERVIEW:

  • Night work on the Service Drives will occur. Service Drive access will be maintained but will be slowed when work is occurring. Please see immediately below for more information.

  • Aside from the additional nighttime lane closures on the Service Drives, there will be no changes to the existing traffic patterns this week, Expect various single lane closures, listed in more detail further below in this section.


NIGHT WORK ON SERVICE DRIVES*
Thursday, September 30 and Friday, October 1, 2021. 7 p.m. - 6 a.m.
*The Service Drives are the roads that provide access into and out of the parking garage under 100 College Street and the Air Rights Garage from the Route 34 corridor, I91 & I95.
 
Nighttime work is scheduled to occur on the Service Drives this week. The work, which is the installation of drainage apparatus, is scheduled to occur overnight on Thursday, September 30 and Friday, October 1. Overnight work hours are between 7 p.m. and 6 a.m. 
 
While service drive access will be maintained when this work occurs, it will be slowed significantly. Service drive access will be reduced to one lane, with alternating use for both in and outbound traffic. Police officers will direct traffic, alternately letting outbound pass and inbound traffic pass.

Please note that these work dates are subject to change.


LANE CLOSURES
Throughout the one-week period of Monday, September 27 and Friday, October 1, 2021 various lane closures may occur on the following roads to accommodate construction:

  • Inbound & Outbound Service Drives: single lane closures on the roads that provide access to parking under 100 College Street and go on to provide access to the Air Rights Garage.
  • State Street & Union Avenue at North Frontage Road: single lane closures near the intersection of Water Street.
  • South Frontage Road: single lane closures may occur on SFR between York Street and South Orange Street.
  • Martin Luther King Jr. Boulevard: single lane closures between Church Street and Orange Street.

WORK HOURS
Downtown Crossing-related work for the one-week of period of Monday, September 27 through Friday, October 1, 2021 will occur during both daytime and nighttime work hours.

Daytime work hours are weekdays between 7 a.m. and 3:30 p.m. 

Nighttime work hours are between 7 p.m. and 6 a.m.

Nighttime work will include the installation of drainage apparatus under the Service Drives.