Our latest SBCTA Today video segment shows users how to navigate our project-specific interactive Google Maps. Users can click through color-coded icons to see current construction activities including closures and detours, and learn about the project itself. Check out the project-specific map (or maps!) from your computer or mobile device and bookmark or save it so you'll always be prepared before you hit the road!
CONSTRUCTION ACTIVITIES
Week of October 19
Crews continue to work on final inspections, complete work on the Joshua Wash Bridge, complete drainage work, remove k-rail, complete metal guard rail installation, and install regulatory signage along the US 395 corridor. Please drive carefully and be alert for crews and equipment.  

Si prefiere recibir información de construcción en español, llame al (877) 55 - SBCTA.
 
Please remember all construction is dynamic and the schedule is weather-permitting and subject to change.
ADJACENT PROJECTS
SR 18 Resurfacing Project Update
In July 2020, Caltrans began a $1.3 million resurfacing on SR 18 from Central Road in Apple Valley to west of Fairlane Road in Lucerne. The repaving portion of this work is complete. Crews are starting additional preventative maintenance activities. Work will occur weekdays from 6:00 a.m. to 6:00 p.m. Most of the work will occur off the roadway; lane re-striping will occur with a moving closure and reduced speed limit. For more information, visit Caltrans District 8 HERE.
ABOUT THE US 395 - PHASE 1 WIDENING PROJECT
US 395 is one of the main north/south highways in southern California providing access to and linking economic centers, recreational areas and urban and rural regions. The project will widen approximately five miles along US 395 between Chamberlaine Way (Adelanto) and SR 18 (Victorville) from two lanes to four lanes and install turn lanes and signals at various intersections within the corridor.