June 21,  2019


What's Happening Now...
Road, Sidewalk and Pathway Construction  
 
The City of Novi prides itself on maintaining open lines of communication and keeping community members apprised of the latest in road and  non-motorized construction projects. 

The following information is intended to provide an overview of current projects.

Please note: All completion dates are merely estimates. Projects could extend beyond those dates due to unforeseen issues with the project and inclement weather.
Oakland County Transportation  Updates


RCOC  began sawcutting and removals of the existing concrete within the center and inside lanes of 12 Mile Road. Removals will continue through this week with preparation for pouring new concrete someone late next week. The project will occur in two stages. During Stage 1, the outside lane of 12 Mile will be open in each direction and only right turns will be allowed from southbound and northbound Novi Road. During Stage 2, one inside lane of 12 Mile will be open in each direction. Novi Road will be completely closed north and south of 12 Mile Road.
Estimated completion date: August 15, 2019

The segments of 10 Mile Road from Meadowbrook to Novi roads, Novi to Taft roads and Taft to Beck roads are now complete with paving. The contractor should have completed the Beck to Wixom roads segment on Wednesday. That leaves just one segment remaining to be paved, which is Wixom to Napier roads. Plans are to have this last segment paved by early next week. Final striping and pavement markings will be placed on all segments by the end of June.
Estimated completion date: July 15, 2019

RCOC  will be doing pavement preventative maintenance on Haggerty Road, from 8 to 9 Mile Roads. The project will involve spot milling of the existing asphalt at curb line and entrance approaches and placing two-inches of asphalt pavement over top the entire road way. Project is expected to start July 15.
Estimated completion date: July 30, 2019

RCOC is having a contractor finish the balance of concrete panel work remaining from the 2018 project which concentrated on the intersection of 12 Mile and Meadowbrook Road. The work is expected to begin after the completion of the 12 Mile and Novi Road intersection.
Estimated completion date: September 14, 2019

RCOC is replacing the existing culverts at two Seeley Drain crossings of Haggerty Road, north of 13 Mile Road and MacKenzie Drive. While under construction, Haggerty Road will be closed at the culvert locations. Project is expected to start July 8.
Estimated completion date: August 16, 2019
City of Novi Projects


Rossdale Court is now complete and Woodside Court was recently poured and waiting on cure strength to fully reopen. Restoration on those streets will follow, shortly. Addington Lane is now complete and fully reopened to traffic. Work has started on Cheyenne Drive with removals of the first half. Cody Lane will follow closely behind Cheyenne.
Estimated completion date: November 1, 2019


Heatherbrae Way S, Siegal Drive/Court, Singh Boulevard and Vero Court are now complete. Restoration, to include irrigation, will be ongoing over the next couple weeks. The contractor is still trying to schedule the milling and paving of Anchorage Court and Crestwood Drive.
Estimated completion date: November 1, 2019 

The first halves of panels on Carlisle Court, Waycroft Drive, Courtview Trail and Roxbury Drive have been completed. Crews are now starting removals on the second halves. Panels on the first halves of Cherry Hill Road and Park Ridge Court have also been removed and replaced and waiting sufficient cure strength to begin on the second halves.
Estimated completion date: November 1, 2019

The contractor has completed the spray patching of all the streets and are expected to begin chip sealing each of those streets on Tuesday or Wednesday next week. The final step of fog sealing should start immediately following the chip sealing.
Estimated completion date: July 15, 2019

Even with all the rain, the contractor has made significant progress removing all the unsuitable soils and nearly half done with its replacement with good, road foundation soils. They are now done with the steel sheeting wall along the north side of Crescent Boulevard and the Industrial Spur. Next will be to install new storm sewer and steel sheeting wall along the eastern side of Crescent Boulevard.
Estimated completion date: November 1, 2019

The City will be rehabbing Cabot Drive, from 12 Mile to 13 Mile Roads and Lewis Drive, from Cabot Drive to Haggerty Road. It will include the milling of the existing concrete road, fixing the existing concrete panel joints and topping the roadways with 3-inches of new asphalt pavement. Project is expected to start July 15.
Estimated completion date: September 15, 2019

The contractor has several shafts constructed for proposed sanitary manholes along Nine Mile which has choked the roadway down to one lane in several areas. Area residents and motorists need to use caution when driving in these areas. Construction of the storm sewer network at Nine Mile and Garfield Roads has also begun which further complicates movement of vehicles in that area. Open cut sections, west of Garfield Road, are expected to begin in late June.
Estimated completion date: January 27, 2020

The City will be performing rehab on 30+ storm sewer manholes located within the South Lake Drive roadway from 13 Mile Road to West Park Drive. No detours will be used, but motorists can expect delays as the contractor moves along the roadway. Project is now expected to start July 8. 
Estimated completion date: August 15, 2019

The City will be doing preventative maintenance on three roadway bridges located on West Park Drive, between 12 Mile and West Road; Meadowbrook Road, between Chattman Drive and Nine Mile Road; and Cranbrooke Drive, between 10 Mile and Village Wood Road. Project is expected to start September 1.
Estimated completion date: November 1, 2019

The City will be upgrading the traffic signals at 14 Mile and Haggerty Roads and Pontiac Trail and Beck Road. Each intersection will be retrofitted with new mast arms and LED signal heads. Also all legs will have updated pedestrian facilities to include new sidewalk ramps and push button crosswalk signals. Project is expected to start July 1.
Estimated completion date: April 1, 2020

The wet spring conditions have made for slow progress on the ITC Corridor Trail from Nine Mile to 11 Mile Road. The boardwalk is nearing completion, which could happen by next week. The entire path from 10 Mile, south to the boardwalk also still needs to be cut.
Estimated completion date: Late July, early August 2019

In August 2012, Novi citizens overwhelmingly passed a road millage allowing for more than $5 million to be used in annual road and pathway investments. Funds will be used to maintain and improve neighborhood (subdivision/side streets) and major municipal roadways (mile roads, Beck Road, etc.), and to make sidewalk and pathway connections. To learn more a bout upcoming projects,  CLICK HERE.