CONSTRUCTION ACTIVITIES -
Week of June 7, 2021
BRIDGE WORK
The week of June 7, crews will continue work on the retaining walls along the EB SR 210 Base Line on-ramp, perform concrete pours on SR 210 at 5th Street, as well as slope paving work at Victoria Avenue and Pioneer Avenue, and continue constructing temporary bridge supports, also known as falsework, at Highland Avenue and Arden Avenue. The following nighttime closures of EB and WB SR 210 are needed to facilitate this work:

  • EB SR 210 Closed at Highland Avenue - Closed overnight from 10:00 p.m. to 5:00 a.m. Monday, June 7 and Tuesday, June 8 (into Wednesday morning). DETOUR: Exit EB SR 210 at Highland Avenue and turn right. Then turn left on Sterling Avenue, left on Pacific Street and left on Arden Avenue to reenter SR 210 via the Arden Avenue on-ramp.

  • WB SR 210 Closed between SR 330 and Highland Avenue - Closed overnight from 10:00 p.m. to 5:00 a.m. Monday, June 7 and Tuesday, June 8 (into Wednesday morning). DETOUR: Motorists will be directed onto NB SR 330, exit Highland Avenue and turn left at the end of the ramp, continue on Highland Avenue to reenter WB SR 210 via the Highland Avenue on-ramp.

  • EB SR 210 Closed at Base Line* - Closed from 10:00 p.m., Tuesday, June 8 to 5:00 a.m., Wednesday, June 9. DETOUR: Exit EB SR 210 at Base Line and turn right at the end of the ramp, turn left on Palm Avenue, then left on 5th Street to reenter EB SR 210. *Closure will not be taken in conjunction with EB SR 210 closure at Highland Avenue.

  • EB SR 210 Closed between Highland Avenue and SR 330 - Closed nightly from 10:00 p.m. to 5:00 a.m. Wednesday, June 9 through Friday, June 11 (into Saturday morning). DETOUR: Motorists will be directed onto NB SR 330, exit Highland Avenue and turn left at the end of the ramp, continue on Highland Avenue to reenter WB SR 210 via the Highland Avenue on-ramp.

Bridge widening activities are underway during daytime and nighttime shifts, at numerous locations throughout the project area, including 5th Street, Pioneer Avenue, Victoria Avenue, Base Line Interchange, and Highland Avenue. Visit the Google map above (project Google map) for the most up-to-date closures scheduled and available detour routes.
SR 210 LANE, CONNECTOR, AND RAMP CLOSURES
Connector Closures:

  • SB SR 330 to WB SR 210
  • Overnight from 10:00 p.m. to 5:00 a.m. Monday, June 7 and Tuesday, June 8 (into Wednesday morning).

Ramp Closures:

  • EB SR 210 On-Ramp and WB SR 210 On-/Off-Ramps at Base Line
  • Nightly from 8:00 p.m. to 6:00 a.m., Monday, June 7 through Thursday, June 10 (into Friday morning).
  • From 9:00 p.m., Friday, June 11 to 7:00 a.m., Saturday, June 12.

  • EB SR 210 Off-Ramp at Base Line
  • From 8:00 p.m., Monday, June 7 to 6:00 a.m., Tuesday June 8 and overnight from 8:00 p.m. to 6:00 a.m. Wednesday, June 9 and Thursday, June 10 (into Friday morning).

  • EB SR 210 On-Ramp at Arden Avenue
  • Nightly from 8:00 p.m. to 6:00 a.m., Monday, June 7 through Thursday, June 10 (into Friday morning).

Please note, nighttime lane/ramp closures may occur intermittently along EB and WB SR 210, between Del Rosa Avenue and I-10, Mondays through Saturdays (into Sunday mornings), from 8:00 p.m. to 6:00 a.m. No two consecutive ramps will be closed at the same time. In addition, crews will continue daytime and nighttime construction activity along SR 210 as well as on local city streets.
LOCAL STREET CLOSURES
Highland Avenue at SR 210 - Lane closures and/or full closure between the EB SR 210 off-ramp and Arden Avenue, nightly from 9:00 p.m. to 6:00 a.m., Monday, June 7 through Wednesday, June 9 (into Thursday morning) and from 9:00 p.m. to 11:59 p.m. on Thursday, June 10.

*Full closures on Highland Avenue will not take place at the same time as on Arden Avenue.


Arden Avenue at SR 210 -
Lane closures and/or intermittent full street closures will take place on Arden Avenue at SR 210 nightly from 9:00 p.m. to 6:00 a.m., Monday, June 7 through Wednesday, June 9 (into Thursday morning) and from 9:00 p.m. to 11:59 p.m. on Thursday, June 10. At least one lane in each direction will remain open on Arden Avenue at SR 210 at all times.

*Full closures on Arden Avenue will not take place at the same time as full closures on Highland Avenue.
SOUND WALLS AND RETAINING WALLS
Crews are starting work to construct new sound walls and/or retaining walls throughout the project corridor. This work will take place Mondays through Saturdays during daytime hours (6:00 a.m. to 4:00 p.m.) and intermittently during nighttime hours (9:00 p.m. to 5:00 a.m.). 
 
For more information on sound wall and retaining wall construction, please call (877) 55-SBCTA or email info@goSBCTA.com.
ABOUT THE PROJECT
The SR 210 Lane Addition and Base Line Interchange Project is designed to provide increased traffic flow throughout this corridor. To eliminate the existing bottleneck and provide lane continuity, the SR 210 will be widened from Sterling Avenue to San Bernardino Avenue in the cities of San Bernardino, Highland, and Redlands, as well as an unincorporated portion of San Bernardino County. Base Line Interchange will also be widened from Buckeye Street to Seine Avenue in the City of Highland, which will include widening three of the four interchange ramps. As the SR 210 Lane Addition and Base Line Interchange projects aligned geographically and shared similar delivery schedules, they were combined for the design, right-of-way, and construction phases to save cost and expedite the schedule. In addition, pavement rehabilitation work was added through a cooperative agreement with Caltrans that includes new concrete pavement between 5th Street and Lugonia Avenue. Adding the pavement rehabilitation work during the Lane Addition and Base Line Interchange projects means one less project that the community will have to navigate around in the future.

Please remember construction is dynamic and the schedule is subject to change.

Sign up for text messages by texting SR210Baseline to (888) 525-1021 (Reply STOP to cancel, text HELP for help. Normal text and data message rates apply.

Si prefiere recibir información de construcción en español, llame al 877-55-SBCTA.