A major project milestone occurred this week when the pre-cast box culvert sections and concrete walls were set in the Spoon Creek channel. Next week, the contractor plans to finish placing fill material around the box culvert and connect two storm sewers. Crews will then focus on grading and placing subbase on 34th Street, preparing for pavement and retaining wall construction.
 
As always, if you have questions or concerns about the project, please do not hesitate to contact a member of our project team