The following is the construction schedule for the Nine Creeks Trail, previously known as the Lakeshore Royal Windsor Hydro One Corridor Multi-Use Trail.
Completed and Open to the Public:
Phase 1 (April-July 2018): Lorne Park Rd to Indian Rd
Phase 2 (July 2018): Truscott Dr to Lorne Park Rd
Phase 3 (September 2018): Whiteoaks Ave to Ravine Dr
Phase 4 (June 2019): Clarkson Rd to Welwyn Dr
Phase 5 (June 2019): Southdown Rd to Bromsgrove Rd
Construction Planned or Underway:
Phase 6 (August 2019): Southdown Rd to Welwyn Dr – completed and opened to the public
Phase 7 (September 2019): Truscott Dr to Whiteoaks Ave
Phase 8 (October 2019): Woodeden Dr and Indian Rd to South Sheridan Way
Phase 9 (August 2019): Clarkson Rd to Ravine Dr - completed and opened to the public
Phase 10 (delayed to Summer 2020 due to Trans Northern Pipeline work): Winston Churchill Blvd. to Bromsgrove Rd.