Despite some unfriendly weather, work continues on O Avenue NW.  The contractor is currently working on sanitary sewer repairs identified during construction, along with remaining water services.  

Over the next two weeks, crews will continue between 16th Street and 18th Street, and will focus on installation of storm sewer, removal of old pavement, grading, and placement of subbase. We may also see water main installation to begin west of 20th Street NW.  

Once all this is complete, pavement construction will begin. We anticipate new pavement on the side streets will be installed sometime mid-June, followed by pavement placement on O Avenue itself.  

As always, please do not hesitate to contact a member of the City’s project team if you have questions or concerns. Thank you for your patience.