Exciting changes coming your way!
π§
With so many closures due to Covid-19 I wanted to update you on our great progress. Sunrise is here for you!! We are continuing our construction projects and our parks are open for passive use. Projects are moving forward and we want Sunrise to continue to be the best it can be for you the residents.
Senior Center Expansion
Kitchen work is approximately 99% complete and the new teaching camera system with monitors has been completed and tested
HVAC is complete
AV System has been installed
New stage stair carpeting is complete
Shell has been completed with the windows and doors installed
Drywall and ceiling grid work completed
HVAC units is operational
New carpeting has been installed in both the Computer Training Room and Game Room
New wall mirrors have been installed
New closets and doors have been constructed
New wooden floor is being installed
Welleby Park Expansion
Restroom Building shell work completed and the metal roof has been installed. Interior drywall installation completed. Building stucco completed and primer coat and final paint completed.
First lift of asphalt for the new roadway and parking area has been installed
Installation of Chain Link Fencing post installation is 85% complete
Irrigation main installation is 75% complete
Concrete seating wall rough construction completed
Installation of the support footings for the water features has been completed and decorative concrete surfacing has been completed
Installation of process tanks is 80% complete
Water Distribution System plumbing is 80% complete
Splash Pad Features have been delivered to the site
Installation of the new Shade System is substantially complete
Installation of the new playground equipment has been completed
Playground curbing has been completed
Safety surface sub-base has been installed
Slabs poured for buildings
First lift of asphalt for the roadway has been installed
Final shop drawing approval for the design and fabrication of the structures is almost completed
Fabrication and installation of the structures is sole sourced by the City under a separate contract. Installation scheduled for summer 2020
Veterans Park
Playground equipment and curbing work is complete
Playground safety surface sub-base is complete
Precast Concrete Wall and Decorative Fence columns have been installed
Installation of the Memorial Monuments are approximately 95% complete
Civic Center Expansion
Roadway β Asphalt Complete
Irrigation β 100% complete
Site Grading β 100% complete
Sidewalks β 100% complete
Landscaping β Plants and sod have been installed and the dry retention area has been constructed. Location, quantities, and costs of mitigation plant material for trees that were removed during construction are still pending.
Interior floor finishes including the wood gym, racquetball court, and fitness area floors have been installed.
The new gym floor has been sealed
The elevator has been completed and approved
Re-roof β 99% complete
Security, access control, and the new main front desk has been installed
The City has begun installing equipment in the exercise area
MORE TO COME! STAY TUNED!!!!!!