New Mary Lyon taking shape

Construction on Mary Lyon is progressing, with the classroom and administrative area taking shape in the middle of the construction zone. Contractors built forms and footings for that area and poured concrete on Wednesday.

They're also digging trenching for utility pipes and electrical conduit feeds. Elevator pit and foundation wall work is planned to continue through the end of November.

Take a look at what the site looks like now.
A concrete  pump truck is used to spread the concrete mix to the various areas of the pour.

A closer look at concrete pouring into a footing.

Doing some of the finishing work after the pour.

Close-up look at a footing.
This Austrian black pine from the old Mary Lyon will be incorporated into the new site.
 
Questions?
Please send questions about the Mary Lyon Elementary School construction project to  [email protected]

Tacoma Public Schools and Building for Achievement logos

Tacoma Public Schools does not discriminate in any programs or activities on the basis of sex, race, creed, religion, color, national origin, age, veteran or military status, sexual orientation, gender expression or identity, disability, or the use of a trained dog guide or service animal and provides equal access to the Boy Scouts and other designated youth groups. 

The following employees have been designated to handle questions and complaints of alleged discrimination: Civil Rights Coordinator: Lisa Nolan, 253-571-1252, [email protected]; Title IX Coordinator: James Neil, 253-571-1123, [email protected]; and 504 Coordinator: Elementary, Steven Mondragon, [email protected], 253-571-1173; Secondary, Jon Bell, [email protected], 253-571-1225. Address: P.O. Box 1357, Tacoma, WA 98401-1357.