Water Supply Program
Quarry/Chattahoochee/Hemphill
|
|
Update:
Crews lined approximately 284 linear feet of the tunnel last week. Crews continue to work on the tunnel extension excavation and have approximately 4,140.5 linear feet remaining.
Controlled blasting at the R.M. Clayton Water Reclamation Center continues, and the construction of the Quarry and Hemphill pump stations are still in progress.
The Water Supply Program will increase Atlanta’s reserve water supply from three to five days to 30 to 90 days. The $300 million investment includes the construction of a five-mile tunnel connecting the Chattahoochee River, the Hemphill Water Treatment Plant and the former Bellwood Quarry which will be transformed into a 2.4-billion-gallon reservoir. The Water Supply Program is scheduled for completion September 2019.
Expected Completion:
September 2019
Project Location:
Northwest Atlanta
Council District(s):
3, 9
Neighborhood Planning Unit(s):
C, D, G, J, K
|
|
Upper Proctor Creek Capacity Relief Project
Rodney Cook Sr. Park In Historic Vine City
|
|
Update
:
Retaining walls around the pond and fountain are complete and work on Walnut Street, Thurmond Street, and Elm Street is ongoing. The construction of the pipes needed to send stormwater into the pond is scheduled to be finished by the end of August. Green infrastructure installation has begun and will continue through the end of the project and landscaping will be installed in Fall 2019 to ensure survival of the plants. Due to extreme wet weather for nearly a year-and-half, the new projected completion of DWM’s work is February 2020.
This project consists of a collection of innovative stormwater practices designed to redirect surface runoff away from the Beckwith Trunk and Mineral Springs combined sewer systems.
The capacity relief facility is currently under construction led by the Astra/Rohadfox, Joint Venture.
The components of this project include a 2-acre pond (9+ MG capacity), green infrastructure (bioretention, stormwater planters, rainwater harvesting cisterns, and soil restoration), aerating water features, separated storm drain pipelines, new sidewalks and roadway improvements.
The Department of Watershed Management is working concurrently with The Trust for Public Land who is responsible for the build out of the adjacent park. In addition, The National Monuments Foundation will be constructing statues of historic figures throughout the finished park.
Expected Completion:
February 2020
Project Location:
Vine Street NW
Council District(s):
3
Neighborhood Planning Unit(s):
L
|
|
Upper Proctor Creek - Boone Boulevard Green Infrastructure & Capacity Relief Project
|
|
Update:
Work progresses on Joseph E. Boone Blvd as contractors continue laying water main pipe from Sunset Avenue towards Joseph E. Lowery Blvd. On the north side of Boone Boulevard, preparation for the addition of 20 new planter boxes and a new sidewalk is underway from Northside Drive towards Sunset Avenue.
This project will provide capacity relief to the North Avenue Combined Sewer Area and water quality improvements using the green infrastructure practice called bioretention, which is a specially landscaped area that captures runoff from an impervious surface and allows water to enter the soil. Proposed bioretention areas will span approximately 1.2 miles along Boone Blvd from Mayson Turner Road to Northside Drive that will collect stormwater runoff from along the sides of the road.
Expected Completion:
September 2019
Project Location:
Northwest Atlanta
Council District(s):
3
Neighborhood Planning Unit(s):
L
|
|
Energy Services Performance Initiatives -
Noresco
|
|
Update:
Crews will begin installation of a new truck scale, dry silo, and UV replacement for channel one at RM Clayton.
Three Energy Conservation Measures (ECM) for a software system to optimize the City's water distribution system is being implemented: A new Class A bio-solids system, office space at RMC WRC, and a replacement of ultraviolet disinfection system with new Trojan UV Signa System.
Expected Completion:
December 2020
Project Location:
R.M. Clayton WRC
Council District(s):
2, 3, 4, 5, 6, 7, 8, 9
Neighborhood Planning Unit(s):
C, D, G
|
|
Energy Services Performance Initiatives -
Schneider
|
|
Update:
Installation of lighting upgrades at the Utoy Creek Plant are near completion; once completed, installation of lighting upgrades at the South River Water Reclamation Center will begin. Also, the remaining ABAC equipment will be delivered to the South River WRC.
Facility infrastructure improvements are underway at the RM Clayton WRC, Hemphill Water Treatment Plant, South River WRC, Utoy Creek WRC, Chattahoochee Water Treatment Plant and 14th St. Admininstration Complex.
Expected Completion
: December 2020
Project Location
: RM Clayton WRC, Hemphill WTP (Settled Solids only), South River WRC, Utoy Creek WRC, Chattahoochee Water Treatment, and 14th St Admin Complex
Council District(s)
: 1, 3, 8, 9, 10
Neighborhood Planning Unit(s)
: C, D, E, G, H, Z
|
|
R.M. Clayton Nutrient Recovery System – Ostara
|
|
Update:
Contractors working on the Nutrient Recovery System Building at the RM Clayton Water Treatment Plant will complete electrical installation and firewall panels inside of building. Crews will also begin installing new geodesic dome on top of digester.
The purpose of this project is to improve nutrient (phosphorus and nitrogen) removal within the RM Clayton WRC. Enhanced nutrient removal will improve permit compliance, reduce chemical and operating costs, and provide a reusable byproduct.
Expected Completion:
September 2019
Project Location:
R.M. Clayton WRC
Council District(s):
2, 3, 4, 5, 6, 7, 8, 9
Neighborhood Planning Unit(s):
C, D, G
|
|
R.M. Clayton Water Reclamation Center (WRC) Instrumentation/Controls Reliability Restoration
|
|
Update:
Crews are currently installing panels and fiber optic cables, as well as conducting factory acceptance testing in order to test the equipment.
The R.M. Clayton Water Reclamation Center Instrumentation/Controls Reliability Restoration project will upgrade various outdated Distributive Control Systems (DCS) and Process Logic Controller (PLC) systems as well as add optical fibers and duct banks at the RM Clayton WRC. These systems monitor and control various process equipment and provide the interconnectivity required to treat wastewater to meet regulatory compliance permits.
Expected Completion
: TBD
Project Location
: Northwest Atlanta
Council District(s)
: 9
Neighborhood Planning Unit(s)
: C, D, G
|
|
Neighborhood Planning Unit (NPU)
The City of Atlanta is divided into 25 Neighborhood Planning Units (NPU), which serve as citizen advisory councils that make recommendations to the Mayor and City Council on zoning, land use, and other planning issues. NPUs also allow citizens to receive information about all functions of city government.
|
|
See neighborhoods located within listed NPUs below:
|
|
NPU-B
- Brookhaven
- Buckhead Forest
- Buckhead Village
- East Chastain Park
- Garden Hills
- Lenox
- Lindbergh/Morosgo
- North Buckhead
- Peachtree Heights East and West
- Peachtree Hills
- Peachtree Park
- Pine Hills
- Ridgedale Park
- South Tuxedo Park
NPU-C
- Arden/Habersham
- Argonne Forest
- Brandon
- Castewood
- Channing Valley
- Collier Hills
- Collier Hills North
- Colonial Homes
- Cross Creek
- Fernleaf
- Hanover West
- Memorial Park
- Peachtree Battle Alliance
- Ridgewood Heights
- Springlake
- Wesley Battlle
- Westminister/Milar
- Westover Plantation
- Wildwood
- Woodfield
- Wyngate
NPU-D
- Berkley Park
- Blandtown
- Bolton
- Hills Park
- Riverside
- Underwood Hills
- Whittier Mill Village
NPU-G
- Almond Park
- Atlanta Industrial Park
- Bolton Hills
- Brookview Heights
- Carey Park
- Carver Hills
- Chattahoochee
- English Park
- Lincoln Homes
- Monroe Heights
- Rockdale
- Scotts Crossing
- West Highlands
NPU-J
- Center Hill
- Dixie Hills
- Grove Park
- Harvel Homes
- Penelope Neighbors
- West Lake
|
|
NPU-K
- Bankhead
- Hunter Hills
- Knight Park/Howell Station
- Mozley Park
- Washington Park
NPU-L
NPU-M
- Castleberry Hill
- Downtown
- Old Fourth Ward
NPU-O
- East Lake
- Edgewood
- Kirkwood
- The Villages at East Lake
NPU-P
- Arlington Estates
- Ashley Courts
- Ben Hill
- Brentwood
- Briar Glen
- Butner/Tell
- Cascade Green
- Deerwood
- Fairburn
- Greenbriar Village
- Heritage Valley
- Huntington
- Kings Forest
- Lake Estates
- Meadowbrook Forest
- Mellwood
- Mt. Gilead Woods
- Niskey Cove
- Niskey Lake
- Princeton Lakes
- Wildwood Forest
NPU-S
- Bush Mountain
- Cascade Avenue/Road
- Fort McPherson
- Oakland City
- Venetian Hills
- Westmont Estates
NPU-T
- Ashview Heights
- Atlanta University Center
- Harris Chiles
- Just Us
- The Villages at Castleberry Hill
- West End
- Westview
|
|
Department of Watershed Management
72 Marietta Street NW
Atlanta, GA 30303
|
|
|
|
|
|
|