MAIN STREET IMPROVEMENT PROJECT
STARTING WORK IN MAPLE & MAIN AREA,
MONDAY APRIL 20
th
The Main Street improvement project will follow a six-phase construction sequence.
The first phase begins Monday, April 20th includes these tasks:
Site preparation, survey layout and CBYD (Call before You Dig) mark out.
Construction work will then begin with new stormwater drainage installation at Main and Maple streets intersection near the flagpole.
The contractor will also fill the voids under the sidewalk on Main between The Villager to Strut Your Mutt. This work must be completed before the second phase can begin which includes removal of the old sidewalk, the installation of electrical conduit, granite curbing new sidewalk, and Belgium blocks.
TRAFFIC: During first phase there will not be any major changes to traffic. Two-way traffic will remain, with an officer on both sides of the work zone to facilitate alternate traffic flow as needed during the work times.
PARKING: There will be some adjustment of parking spaces while the drainage is being worked on, but there should not be blockage of the sidewalk during this time.
WORK HOURS: Work hours will be 7:30-5 Monday through Friday, although the construction company may work on Saturdays while the retail shops are closed. The company is being given a list of the restaurants who are open for take out and delivery and will make all efforts not to interfere with any business going on.
Once the contractor is fully mobilized and crews are underway more information will be shared on traffic control, parking and contractor’s work schedule. More information to come soon!