PAVING FOR PROGRESS
E Avenue NW       


Construction Update: 8-15-18
 
The project on E Ave NW is underway and things are progressing as scheduled.

Improvements include: 
  • Concrete pavement reconstruction of E Avenue NW from the future Highway 100 entrance to Stoney Point Road, and Stoney Point Road from E Avenue to the Cherry Hill Park entrance. 
  • The road will be upgraded to include curb, gutter and storm sewer. 
  • Sidewalk will also be extended on the south side of E Avenue between Rockvalley and Stoney Point, and portions of sidewalk will be installed on Stoney Point in coordination with a future trail project. 
  • A roundabout will be installed at the intersection of E Avenue with Stoney Point.
The contractor is currently working on removing the existing gravel road and installing new storm sewer pipes. 

Coming up next, the intersection of Limerock Dr. and E Ave will be under construction; road closures will be in effect during this time.

Please continue to set your garbage and recycling bins out on their normal collection day; the contractor is responsible for moving them to a location for pickup and returning them to you.
Thank you for your patience as we continue this project!
 

Contractor 
Rathje Construction
319-377-3179

City Construction Inspector
Jeremy Blok
319-775-3386