Water Supply Program
Quarry/Chattahoochee/Hemphill
|
|
Update:
The tunnel lining operations are still underway and is near completion.
The construction activities at the Quarry and Hemphill pump stations continue.
The Water Supply Program will increase Atlanta’s reserve water supply from three to five days to 30 to 90 days. The $320 million investment includes the construction of a five-mile tunnel connecting the Chattahoochee River, the Hemphill Water Treatment Plant, and the former Bellwood Quarry, which will be transformed into a 2.4-billion-gallon reservoir. The Water Supply Program is currently scheduled for completion in February 2020.
Expected Completion:
February 2020
Project Location:
Northwest Atlanta
Council Districts:
3, 9
Neighborhood Planning Units:
C, D, G, J, K
|
|
Dekalb Avenue Water Main Installation & Resurfacing Project
|
|
Update:
Crews have completed all the main installation on the Dekalb Avenue project, and are performing site restoration
The City of Atlanta Department of Watershed Management will upgrade sections of the water main along Dekalb Avenue, between Dekalb Place NE and Oxford Place NE and again between Moreland Avenue and Ferguson Street, totaling approximately 1400 linear feet of water main. The goal is to upgrade the existing main, which will improve water flow and quality. This project is a part of a continuous effort to maintain and upgrade the City of Atlanta’s aging infrastructure. Once the water main installation is complete, the Renew Atlanta Bond program will begin the asphalt resurfacing portion of the project
Expected Completion:
October 2019
Project Location:
Northeast Atlanta
Council Districts:
2, 5
NPU:
N
|
|
Upper Proctor Creek Capacity Relief Project
Rodney Cook Sr. Park In Historic Vine City
|
|
Update
: Retaining walls around the pond and fountain are complete and work on Walnut Street, Thurmond Street, and Elm Street is ongoing. The construction of the pipes needed to send stormwater into the pond is complete. Green infrastructure installation has begun and will continue through the end of the project. Landscaping will be installed in Fall 2019 to ensure survival of the plants. Due to extreme wet weather for nearly a year-and-half, the new projected completion of DWM’s work is February 2020
This project consists of a collection of innovative stormwater practices designed to redirect surface runoff away from the Beckwith Trunk and Mineral Springs combined sewer systems.
The capacity relief facility is currently under construction led by the Astra/Rohadfox, Joint Venture.
The components of this project include a 2-acre pond (9+ MG capacity), green infrastructure (bioretention, stormwater planters, rainwater harvesting cisterns, and soil restoration), aerating water features, separated storm drain pipelines, new sidewalks and roadway improvements.
The Department of Watershed Management is working concurrently with The Trust for Public Land who is responsible for the build out of the adjacent park. In addition, The National Monuments Foundation will be constructing statues of historic figures throughout the finished park.
Expected Completion:
February 2020
Project Location:
Vine Street NW
Council District:
3
Neighborhood Planning Unit:
L
|
|
Upper Proctor Creek - Boone Boulevard Green Infrastructure & Capacity Relief Project
|
|
Update:
Work progresses on Joseph E. Boone Boulevard as contractors continue to install a water main pipe from Sunset Avenue towards Joseph E. Lowery Blvd. On the north side of Boone Boulevard, contractors continue the installation of 20 new planter boxes and a new sidewalk from Northside Drive towards Sunset Avenue.
This project will provide capacity relief to the North Avenue Combined Sewer Area and water quality improvements using the green infrastructure practice called bioretention, which is a specially landscaped area that captures runoff from an impervious surface and allows water to enter the soil. Proposed bioretention areas will span approximately 1.2 miles along Boone Blvd from Mayson Turner Road to Northside Drive that will collect stormwater runoff from along the sides of the road.
Expected Completion:
March 2020
Project Location:
Northwest Atlanta
Council District(s):
3
Neighborhood Planning Unit(s):
L
|
|
Energy Services Performance Initiatives – Noresco
|
|
Update:
Contractors continue work on the dryer building at RM Clayton in anticipation of the first dryer parts arriving onsite in early October.
Three Energy Conservation Measures (ECM) for a software system to optimize the City's water distribution system is being implemented: A new Class A bio-solids system, office space at RMC WRC, and a replacement of ultraviolet disinfection system with new Trojan UV Signa System.
Expected Completion:
December 2020
Project Location:
R.M. Clayton WRC
Council Districts:
2, 3, 4, 5, 6, 7, 8, 9
Neighborhood Planning Units:
C, D, G
|
|
Energy Services Performance Initiatives – Schneider
|
|
Update:
Contractors at Utoy Creek have completed the installation of one sludge thickener. Crews have begun lighting upgrades at the South River Water Reclamation Center.
Facility infrastructure improvements are underway at the RM Clayton WRC, Hemphill Water Treatment Plant, South River WRC, Utoy Creek WRC, Chattahoochee Water Treatment Plant and 14th St. Administration Complex.
Expected Completion
: December 2020
Project Location
: RM Clayton WRC, Hemphill WTP (Settled Solids only), South River WRC, Utoy Creek WRC, Chattahoochee Water Treatment, and 14th St. Admin Complex
Council Districts
: 1, 3, 8, 9, 10
Neighborhood Planning Units
: C, D, E, G, H, Z
|
|
R.M. Clayton Nutrient Recovery System – Ostara
|
|
Update:
Contractors at RM Clayton are working on the geodesic dome that will cover the digester. Indoor mechanical installation and electrical installation on the Nutrient Recovery System Building will be completed in October.
The purpose of this project is to improve nutrient (phosphorus and nitrogen) removal within the R.M. Clayton WRC. Enhanced nutrient removal will improve permit compliance, reduce chemical and operating costs, and provide a reusable byproduct.
Expected Completion:
October 2019
Project Location:
R.M. Clayton WRC
Council Districts:
2, 3, 4, 5, 6, 7, 8, 9
Neighborhood Planning Units:
C, D, G
|
|
R.M. Clayton Water Reclamation Center (WRC) Instrumentation/Controls Reliability Restoration
|
|
Update:
Crews are currently working to install root switch and edge switch filters.
The R.M. Clayton Water Reclamation Center Instrumentation/Controls Reliability Restoration project will upgrade various outdated Distributive Control Systems (DCS) and Process Logic Controller (PLC) systems, as well as add optical fibers and duct banks at the RM Clayton WRC. These systems monitor and control various process equipment and provide the interconnectivity required to treat wastewater to meet regulatory compliance permits.
Expected Completion:
February 2020
Project Location:
Northwest Atlanta
Council District:
9
Neighborhood Planning Units:
C, D, G
|
|
Neighborhood Planning Unit (NPU)
The City of Atlanta is divided into 25 Neighborhood Planning Units (NPU), which serve as citizen advisory councils that make recommendations to the Mayor and City Council on zoning, land use, and other planning issues. NPUs also allow citizens to receive information about all functions of city government.
|
|
See neighborhoods located within listed NPUs below:
|
|
NPU-B
- Brookhaven
- Buckhead Forest
- Buckhead Village
- East Chastain Park
- Garden Hills
- Lenox
- Lindbergh/Morosgo
- North Buckhead
- Peachtree Heights East and West
- Peachtree Hills
- Peachtree Park
- Pine Hills
- Ridgedale Park
- South Tuxedo Park
NPU-C
- Arden/Habersham
- Argonne Forest
- Brandon
- Castewood
- Channing Valley
- Collier Hills
- Collier Hills North
- Colonial Homes
- Cross Creek
- Fernleaf
- Hanover West
- Memorial Park
- Peachtree Battle Alliance
- Ridgewood Heights
- Springlake
- Wesley Battlle
- Westminister/Milar
- Westover Plantation
- Wildwood
- Woodfield
- Wyngate
NPU-D
- Berkley Park
- Blandtown
- Bolton
- Hills Park
- Riverside
- Underwood Hills
- Whittier Mill Village
NPU-G
- Almond Park
- Atlanta Industrial Park
- Bolton Hills
- Brookview Heights
- Carey Park
- Carver Hills
- Chattahoochee
- English Park
- Lincoln Homes
- Monroe Heights
- Rockdale
- Scotts Crossing
- West Highlands
NPU-J
- Center Hill
- Dixie Hills
- Grove Park
- Harvel Homes
- Penelope Neighbors
- West Lake
|
|
NPU-K
- Bankhead
- Hunter Hills
- Knight Park/Howell Station
- Mozley Park
- Washington Park
NPU-L
NPU-M
- Castleberry Hill
- Downtown
- Old Fourth Ward
NPU-O
- East Lake
- Edgewood
- Kirkwood
- The Villages at East Lake
NPU-P
- Arlington Estates
- Ashley Courts
- Ben Hill
- Brentwood
- Briar Glen
- Butner/Tell
- Cascade Green
- Deerwood
- Fairburn
- Greenbriar Village
- Heritage Valley
- Huntington
- Kings Forest
- Lake Estates
- Meadowbrook Forest
- Mellwood
- Mt. Gilead Woods
- Niskey Cove
- Niskey Lake
- Princeton Lakes
- Wildwood Forest
NPU-S
- Bush Mountain
- Cascade Avenue/Road
- Fort McPherson
- Oakland City
- Venetian Hills
- Westmont Estates
NPU-T
- Ashview Heights
- Atlanta University Center
- Harris Chiles
- Just Us
- The Villages at Castleberry Hill
- West End
- Westview
|
|
Department of Watershed Management
72 Marietta Street NW
Atlanta, GA 30303
|
|
|
|
|
|
|