Work is moving forward on C Street, with the contractor working on pouring concrete as well as finishing up utilities. From north to south, here’s a quick summary: 

  • Between Rapids Avenue and Hawthorne Drive: crews are pouring new concrete on the west side of the street. The traffic pattern will soon shift so they can continue working on the other side of the street. 
  • Between Lauren Drive and Fruitland Blvd: crews continue to work on underground utilities. This is anticipated to last approximately two months, before crews will transition to paving. 

C Street remains closed to through traffic, with business and residential access open. The project is on track to be completed by this fall. As always, thank you for your patience.