Work continues to move forward on Midway Drive. The contractor has almost completed water main installation, and will soon begin replacing water services and placing storm sewer. This work will start at Jacolyn Drive and move toward West Post Road. 

The road remains open to property owners only (local traffic); all other traffic is required to detour. 

Later this summer, following the completion of the water main and storm sewer, the road will close to all vehicles while pavement work takes place. On-street parking on neighborhood side-streets will still be available, and we will send additional updates as this phase gets closer. 

The project is on schedule and will wrap up this fall. We appreciate your patience while we complete this work.

If you have any questions, please don’t hesitate to contact us!