Kerr Contractors is constructing the new retaining walls adjacent to the bridges.
Oregon State Bridge, the bridge subcontractor for the 198th Avenue project, completed the installation of bridge pile and sheet piles for both bridges, and is currently building bridge abutments and related wing walls.
PGE has completed pole relocations north of Butternut Creek and is now working on installations of poles south of Jaylee Street.
The electrical subcontractor for the project are beginning the installation of electrical conduit runs for new street lighting between Farmington Road and Oak Street.