We wanted to provide you with an update on the Midway Drive project.

The north half of Midway Drive between West Post Road and Jacolyn Drive has been paved. The contractor is working on paving intersections and driveways; once that work is complete, they will transition to paving the south half of Midway Drive.

Water main installation has been completed between Jacolyn Drive and Peace Avenue, and also on Zelda Drive. The contractor will soon begin replacing residential water lines, which will require temporary interruption in water service. Residents will receive notification with an anticipated timeline of when their water service will be replaced, and should expect a few hours of water service interruption.

Midway is open to property owners only; this traffic pattern will continue until pavement removal begins following all utility installations.

As always, we appreciate your patience. Please do not hesitate to contact us if you have any questions or concerns.