Houston, TX - Houston City Council Member Dave Martin is pleased to announce Houston Public Works crews will be in the Freeway Manor area to make repairs to an existing sidewa
lk on the south side
of Rodney Street and the east side of Shawnee Street.
Construction is scheduled to begin on
Thursday, January 3
, 2019, and is expected to be completed by the end of March 2019, weather permitting. The project will start at 2307 Rodney Street, and crews will work their way towards 1022 Shawnee Street.
The project's scope of work includes removing the existing 4 foot sidewalk and replacing it with a 5 foot sidewalk, and installing the safe sidewalk across driveways. Should any damage to private property occur as a result of the project, please contact the District E office immediately for assistance with repair. Per the City of Houston contract, the City is responsible for leaving property in a construction zone in better, if not the same, condition as it was before construction began.