The MPO area boundary has changed and we will have to update our maps and documents to include the added area.
|
|
In the new area boundary agreement between Harlingen-San Benito Metropolitan Planning Organization and the Brownsville Metropolitan Planning Organization, the HSBMPO has assumed the responsibility of continuing and completing the widening of US 281 project.
|
|
2019-2022 TIP Document Update &
2015-2040 MTP Document Update
|
|
The 2019-2022 TIP has been revised to reflect the comments/suggestion from TxDOT, change the Transit TIP as requested by Valley Metro, and to update the MPO Boundary Map. The updated documents can be viewed at
www.hsbmpo.org
Document update:
- Update MPO boundary in the document and the document map
Mobility Projects:
- South Parallel Corridor Phase II funding cost and the project limits have been updated;
- Stuart Place Road project limits have been updated
Transit Projects:
The 2015-2040 MTP is being revised to reflect the changes made to the TIP and update MPO Boundary Map.The updated documents can be viewed at
www.hsbmpo.org
- Adding US 281 project;
- South Parallel Corridor Phase II funding and cost and the project limits have been updated;
- Stuart Place Road project limits have been updated;
- South Parallel Corridor Phase III funding has been updated;
- Updated MPO boundary in the document and the document maps
|
|
Transportation
Policy Committee
Meeting Date Changes
|
|
The HSBMPO TPC has agreed to move the monthly meetings from the second Wednesday to the third Wednesday of the month. These changes will commence January 2019.
|
|
TxDOT SH 107 Project Update
|
|
Working Days: 285
Began: Aug. 2017
Completion Date: February 2019
|
|
TxDOT SH 345 Overlay Project Update
|
|
Working Days: 80 days
Began: April 2018
Project Completion Date: October 2018
|
|
DATE:
October 1, 2018
Harlingen-San Benito MPO
|
|
Project Status Report:
CONSTRUCTION PROJECTS
(
ESTIMATED TOTAL COST $42.6 Million
)
|
|
A)
FM 106: Roadway Reconstruction (CSJ: 2243-01-009)
|
|
Cost: $ 15,555,191
Contractor: Texas SAI, Inc.
September 2014 Letting
Est. Completion Date: Feb. 2018
Project Manager: David Vera, P.E.
|
|
Project Length: 11.4 MILES
Working days: 420 Days (21 months)
Work Started: November 9, 2015
Preconstruction Meeting: Sept 17, 2015
|
|
Limits: From FM 1847 to FM 510
This project consists of reconstructing an existing roadway consisting of: Roadway Realignment, Drainage Structures, Lime Treatment, Subgrade, Flexible Base, Asphaltic Concrete Pavement, Signing, Pavement Markings & Striping
89 % Complete
156 % Time Used
|
|
B)
BSIF AT LOS INDIOS (CSJ: 0921-06-208)
|
|
Cost: $ 6,949,740
Contractor: Foremost Paving, Inc.
August 2014 Letting
Est. Completion Date: March 2018
Project Manager: Sergio Sustaita, P.E.
|
|
Project Length: .001 MILES
Working days: 262 Days (13 months)
Work Started: February 23, 2015
Preconstruction Meeting: January 8, 2015
|
|
Limits: At Los Indios Free Trade International Bridge
This project consists of the construction of a Border Safety Inspection Facility (BSIF) (Phase I): Drainage Structures, Lime Treatment, Subgrade, Flexible Base, Asphaltic Concrete Pavement, Concrete Pavement (Continuously Reinforced) (10”), Signing, Pavement Markings & Striping.
79 % Complete
153 % Time Used
|
|
C)
Bridge Rehabilitation - Rio Hondo Lift Bridge (CSJ: 0630-02-041)
|
|
Cost: $12,406,043.30 Contractor: PCL Civil Contractors, Inc.
July 2015 Letting
Est. Completion Date: February 2018
Project Manager: Sergio Sustaita, P.E.
|
|
Project Length: 0.117 MILES
Working days: 651 Days (33 months)
Work Started: June 2016
Preconstruction Meeting: April 26,2016
|
|
This project consists of bridge rehabilitation consisting of: Structural, mechanical, and electrical rehabilitation, fender repairs, bridge railing retrofit and channel bank improvements
100 % Complete
99 % Time Used
|
|
D)
US 281 Roadway Rehabilitation and Widening (CSJ: 0220-03-030)
|
|
Cost: $3,939,634 Contractor: Foremost Paving Inc.
October 2016 Letting
Est. Completion Date: July 2018
Project Manager: Candido Bocanegra, P.E.
|
|
Project Length: 1.65 Miles
Working days: 320
Work Started: February 2017
Preconstruction: January 2, 2017
|
|
This project consists of rehabilitation and widening of existing road consisting of:
Grading, Lime Treatment, Subgrade, Flexible Base, Asphaltic Concrete Pavement, Pavement Markings & Striping. Limits: From FM 509 to .05 miles west of FM 1479
95 % Complete
98 % Time Used
|
|
E)
State Highway 107 (CSJ:0342-04-032)
|
|
Cost: $3,712,016 Contractor: Foremost Paving
April 2017 Letting
Est. Completion Date: October 2018
Project Manager: Sergio Sustaita, P.E.
|
|
Project Length: 0.465 Miles
Working days: 285
Work Started: August 2017
Preconstruction: July 11, 2017
|
|
This project consists of construction of a non-freeway facility consisting of widening, retaining walls, storm drain, curb & gutter, signals, signs and pavement markings.
58 % Complete
69 % Time Used
|
|
DESIGN PROJECTS (ESTIMATED TOTAL COST $ 57.9 MILLION)
|
|
1. South Parallel Corridor: CSJ: 0921-06-252 New Construction
This project consists of a new roadway connecting the South Parallel Corridor from FM 509 to FM 1577. Proposed typical sections will be given out at a later date. The current estimated cost is $7,500,001. This project has a tentative letting date of June 2021.
2. Stuart Place Road – Sidewalks CSJ: 0921-06-311 New Construction
This project consists of the construction of new 5 to 6 ft. sidewalks from .18 miles North of Primera Rd. to FM 2994/Wilson Rd. The current estimated cost is $525,392. This project has a tentative letting date of April 2020.
3. SH 107 CSJ: 0342-03-037 Reconstruction
This project consists of the reconstruction of SH 107 to 4 lanes from Louisiana St. to Hooks E. Hodges St. The current estimated cost is $10,185,300. This project has a tentative letting date of Jan. 2021.
4. FM 509 Extension CSJ: 0921-06-254
This project consists of a 2 lane rural roadway extension of FM 509 from FM 508 to FM 1599. The current estimated cost is 6,600,000. This project has a tentative letting date of Jan. 2021.
5. IH-69E CSJ: 0327-08-092
This project consists of the reversal of northbound ramps on IH 69E from Industrial Blvd to Loop 499. The current estimated cost is 2,758,554. This project has a tentative letting date of Jan. 2021.
6. SL 499 CSJ: 1137-02-038
This project consists of the construction of a 6 lane roadway with a raised median from IH-69E to SS206. The current estimated cost is 15,000,000. This project has a tentative letting date of May 2021.
7. BUS 77 CSJ: 0039-12-254
This project consists of the construction of a raised median from Commerce St. to Arroyo Bridge. The current estimated cost is $708,434. This project has a tentative letting date of May 2021.
8. BUS 77 CSJ: 0327-08-098
This project consists of the construction of a raised median from FM 507 to Commerce Street. The current estimated cost is $5,101,566. This project has a tentative letting date of May 2021.
9. Teege Rd. Bridge & Approaches CSJ: 0921-06-302, etc
This project consists of the reconstruction of the bridge and approaches that are located 0.3 miles west of Junction IH-69E. The current estimated cost is $375,000. This project has a tentative letting date of June 2021.
10. FM 1846 Rehabilitation CSJ: 1065-02-039
This project consists of the rehabilitation of FM 1846 from San Jose Ranch to Business 77. The current estimated cost is $1,864,509. This project has a tentative letting date of November 2021.
11. Spur 54 Widening CSJ: 0039-20-008
This project consists of the widening of Spur 54 from Chester Park Rd. to IH-69E SB Frontage Rd. The current estimated cost is $7,341,446. This project has a tentative letting date of April 2021.
|
|
Technical Advisory Committee (TAC) Meetings
Location:
Lon C. Hill Building, 502 E Tyler St., Harlingen TX 78550
Time:
10:00 AM
Upcoming Meeting Dates
: November 15, 2018
Updated
, December 5, 2018, January 2, 2018
|
|
Transportation Policy Committee (TPC) Meetings
Location
: San Benito City Hall, 401 N Sam Houston Blvd., San Benito, TX 78586
Time
: 1:00 PM
Upcoming Meeting Dates
:
November 14, 2018
Canceled
, December 19, 2018, January 16, 2019
|
|
Upcoming Transportation Events
|
|
Transportation Research Board (TRB)
The Transportation Research Board (TRB) 98th Annual Meeting will be held January 13–17, 2019, at the Walter E. Washington Convention Center, in Washington, D.C. The information-packed program is expected to attract more than 13,000 transportation professionals from around the world.
The meeting program will cover all transportation modes, with more than 5,000 presentations in nearly 800 sessions and workshops, addressing topics of interest to policy makers, administrators, practitioners, researchers, and representatives of government, industry, and academic institutions. A number of sessions and workshops will focus on the spotlight theme for the 2019 meeting: Transportation for a Smart, Sustainable, and Equitable Future
Date:
January 13-17, 2019
Location:
Walter E. Washington Convention Center,
801 Mt Vernon Pl NW, Washington, DC 20001
|
|
|
|
|
|
|