November 22, 2019
Please read this important update from Sea Pines CSA regarding the planned roadway reconstruction of Greenwood Drive from Governors Road to Plantation Drive intersection.
As you may be aware, select roadways in Sea Pines are set to undergo major roadway and infrastructure repairs/improvements in 2019 and beyond. This work will improve the drainage and the safety of these roadways. In early 2019, Sea Pines CSA completed Phase 1 of the Greenwood Drive roadwork project along Greenwood Drive, from Club Course Drive to Governors Road.
Beginning Monday, November 25, 2019, at 8:00 AM, Sea Pines CSA will begin Phase 2 of the Greenwood Drive Road Reconstruction Project, along Greenwood Drive, from Governors Road to Plantation Drive intersection.
The first step in this project is the installation of erosion control and tree protection. This will occur next week, weather permitting and is not anticipated to cause any major disruption in traffic.
The entire project is expected to take approximately 12-14 weeks to complete, weather permitting.
Greenwood Drive Phase 2 Information:
Greenwood Drive from Governors Road to Plantation Drive Intersection
Current Status:
- This area of Greenwood Drive is in need of infrastructure repairs and reconstruction
- The useful life of this roadway has exceeded the initial design
- The existing pavement is in poor condition
Project Goals:
Reconstruction of Greenwood Drive from Governors Road to Plantation Drive to include:
- Stabilize roadway to extend road life
- Replace curbing at necessary locations
- Improve traffic flow and safety
- Improve and increase drainage efficiency
- Reconfigure the intersection at Plantation Drive and Greenwood Drive to improve safety
- Replace Pedestrian and Vehicular Guardrails near Six Oaks Cemetery
Phase 2 Traffic Management Plan:
- Work will be performed Monday-Friday from 8 am-5 pm with no work occurring on major holidays. Weekend work may be necessary, but will be communicated in advance.
- During work times, we will employ alternating single lane closures on the portion of Greenwood Drive, from Governors Road to Plantation Drive. Flag persons will be present to control traffic.
- Signage will be placed throughout the work zone and at various locations within the community, to communicate project messages.
- Motorists should expect traffic delays. The project area is considered an active work zone. Please use caution while in driving in this area. To avoid the project area, please use the Ocean Gate.
- Please observe and obey all traffic management personnel, signage and devices.
Phase 2 Traffic Management Plan Diagram: