Dear Parents,
Our campus has been a hub of construction activity all summer. Our general contractor, GMH, and their subcontractors continue to surmount all obstacles in order to bring these projects to completion in record time. Here is an update on the progress:
- The rebuild of the Kindergarten and Second Grade classrooms will be complete and ready for Mrs. Haley and Mrs. Szczech to move into by next week.
- The installation of the new HVAC system that includes air conditioning for the entire main building has been a huge undertaking. The two sub-contractors for this project are both school parents. Shawn Roy of Roy Mechanical is installing the system and McDonell Electric is providing the electrical work. The project is slated to be finished by the opening of school.
- The paved covered eating area with solar power (also McDonell Electric) should be completed by early September.
- The completion of our beautiful preschool building is projected for mid-October.
- The renovation of the black-top will take place once the temporary preschool modular has been removed.
I thank you in advance for your continued patience as we look forward to the day when our campus is fully restored, pristine, and better than ever.
I am pleased to announce that St. Rose will be partnering with Epicurean Group for our hot lunch program this year. Epicurean is the same organization that has been providing food service to Cardinal Newman High School. They will be offering a kid-friendly, organic, hot meal to our students each day, with fresh house-made pizza every Wednesday. In addition, the ordering process is now online.
I look forward to reconnecting with you in the weeks to come.
Kathy Ryan
Principal